To meet the minimum requirements for applying the progress theme, what must be considered?

How lessons will be learned
How lessons will be learned
How time-driven reports will be produced
How time-driven reports will be produced
Which management products will be baselined
Which management products will be baselined
Who is responsible for reporting on progress
Who is responsible for reporting on progress
Suggested answer: B
Explanation:

To meet the minimum requirements for applying the Progress theme in PRINCE2, it must be considered how time-driven reports will be produced. This involves defining the frequency and format of progress reports to ensure that project performance and progress against plans can be effectively monitored and controlled throughout the project.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
Kaisheng Wang
32 questions

Question 172

Report Export Collapse

Which is a purpose of the 'initiating a project' process?

To decide if it is worthwhile to initiate a project
To decide if it is worthwhile to initiate a project
To decide on the project approach
To decide on the project approach
To establish solid foundations for a project
To establish solid foundations for a project
To identify the number of work packages required
To identify the number of work packages required
Suggested answer: C
Explanation:

The purpose of the 'Initiating a Project' process in PRINCE2 is to establish solid foundations for the project, ensuring that there is a common understanding of the reasons for the project, the expected benefits, how it will be managed, and what its products should deliver.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Sean Kell
46 questions

Question 173

Report Export Collapse

Which is a step in the recommended approach to 'defining and analyzing the products'?

Preparing estimates
Preparing estimates
Designing a plan
Designing a plan
Writing a project product description
Writing a project product description
Identifying activities and dependencies
Identifying activities and dependencies
Suggested answer: C
Explanation:

A key step in the recommended approach to 'defining and analyzing the products' in PRINCE2 is writing a Project Product Description. This description captures the purpose, composition, derivation, and acceptance criteria of the project's main deliverable.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Amir Arefi
37 questions

Question 174

Report Export Collapse

Which is a purpose of the 'directing a project' process?

To exercise overall control over the project
To exercise overall control over the project
To take corrective action to control risks and issues
To take corrective action to control risks and issues
To do the minimum in order to decide whether the project is feasible
To do the minimum in order to decide whether the project is feasible
To update the project plan before the next stage
To update the project plan before the next stage
Suggested answer: A
Explanation:

The purpose of the 'Directing a Project' process in PRINCE2 is for the project board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This process includes decision-making on project initiation and continuation, as well as providing overall guidance on policy and standards.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
tirou RANGA
45 questions

Question 175

Report Export Collapse

How does the use of product descriptions support the 'focus on products' principle?

By documenting the scope tolerance for the project
By documenting the scope tolerance for the project
By documenting the quality expected by the customer
By documenting the quality expected by the customer
By documenting the costs for the product
By documenting the costs for the product
By documenting the delivery date for the product
By documenting the delivery date for the product
Suggested answer: B
Explanation:

The use of product descriptions supports the 'focus on products' principle by documenting the quality expectations set by the customer or stakeholders. These descriptions ensure that everyone involved understands what needs to be delivered and to what standards, thereby aligning project outputs with stakeholder needs and expectations.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Maritza Van Der Merwe
48 questions

Question 176

Report Export Collapse

Which describes a risk event?

The area of uncertainty in terms of the threat or opportunity
The area of uncertainty in terms of the threat or opportunity
The derivation or sources of a potential risk to the project
The derivation or sources of a potential risk to the project
The achievement of a milestone on the project plan
The achievement of a milestone on the project plan
The sequence of events and actions that will be put in place if a risk occurs
The sequence of events and actions that will be put in place if a risk occurs
Suggested answer: A
Explanation:

A risk event in PRINCE2 is described as the area of uncertainty in terms of the threat or opportunity. It specifically refers to a specific set of circumstances that may occur and impact the project if the risk materializes. This description encapsulates the nature of a risk as being either a potential threat or an opportunity based on uncertain events that might affect project objectives.

Reference: PRINCE2 7 Foundation handbook and official documents.

asked 23/09/2024
Liaqat Bashir
40 questions

Question 177

Report Export Collapse

Which is a minimum requirement for applying the plans theme?

The project must have at least two management stages
The project must have at least two management stages
The team managers in the project must prepare team plans
The team managers in the project must prepare team plans
Scope tolerance must be prioritized using MoSCoW
Scope tolerance must be prioritized using MoSCoW
The project plan must be presented as a Gantt chart
The project plan must be presented as a Gantt chart
Suggested answer: B
Explanation:

A minimum requirement for applying the Plans theme in PRINCE2 is that team managers in the project must prepare team plans. This ensures that each part of the project controlled by a team manager is adequately planned in line with the overall project plan and stage plans. These team plans provide detailed guidance on how products will be delivered within the constraints set by the project management.

Reference: PRINCE2 7 Foundation resources and study materials.

asked 23/09/2024
Saptarshi Biswas
36 questions

Question 178

Report Export Collapse

Which theme estimates the cost of delivering the project?

Business case
Business case
Change
Change
Plans
Plans
PROGEESS
PROGEESS
Suggested answer: C
Explanation:

The Plans theme in PRINCE2 estimates the cost of delivering the project. This theme involves the preparation and maintenance of the necessary schedules and budgets to control the project, including outlining how, when, and by whom the project's products will be delivered and at what cost.

Reference: PRINCE2 7 Foundation handbook and documents.

asked 23/09/2024
David Kimovec
40 questions

Question 179

Report Export Collapse

Which level of management sets the project level tolerances?

Project board
Project board
Team manager
Team manager
Corporate, programme management or the customer
Corporate, programme management or the customer
Project manager
Project manager
Suggested answer: C
Explanation:

The level of management that sets the project level tolerances in PRINCE2 is corporate, programme management, or the customer. These project-level tolerances are defined to set the allowable limits of variation for the project's objectives, which the Project Manager must work within. This helps ensure that the project remains aligned with strategic goals and customer or corporate standards.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
NAKAYAMA HIROYUKI
41 questions

Question 180

Report Export Collapse

Identify the missing word in the following sentence.

A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

benefits
benefits
dis-benefits
dis-benefits
issues
issues
risks
risks
Suggested answer: A
Explanation:

In PRINCE2, a project's benefits are defined as the measurable improvements that result from the outcomes achieved through the use of the project's outputs. These benefits should align with the objectives set out in the business case and are an essential part of the project's value proposition.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.