If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

A.
Appointing the project board and producing the project brief
A.
Appointing the project board and producing the project brief
Answers
B.
Planning the initiation stage and appointing the project manager
B.
Planning the initiation stage and appointing the project manager
Answers
C.
Producing the additional role descriptions and validating the project product description
C.
Producing the additional role descriptions and validating the project product description
Answers
D.
Verifying the project approach and capturing previous lessons
D.
Verifying the project approach and capturing previous lessons
Answers
Suggested answer: D

Explanation:

If a project is part of a programme, the activities related to verifying the project approach and capturing previous lessons in the 'Starting up a Project' process are most likely to be reduced or eliminated. This reduction occurs because the programme likely provides a strategic framework and lessons learned that the project can adopt directly.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is part of quality control?

A.
Undertaking quality reviews
A.
Undertaking quality reviews
Answers
B.
Writing product descriptions
B.
Writing product descriptions
Answers
C.
Providing assurance that the project is being conducted properly
C.
Providing assurance that the project is being conducted properly
Answers
D.
Documenting the customer's quality expectations
D.
Documenting the customer's quality expectations
Answers
Suggested answer: A

Explanation:

Part of quality control within PRINCE2 involves undertaking quality reviews. These reviews are essential for ensuring that the project's outputs meet the required quality standards and are fit for purpose, aligning with the defined quality criteria set out in the product descriptions.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which theme verifies that a project's products are fit for purpose?

A.
Business case
A.
Business case
Answers
B.
Organization
B.
Organization
Answers
C.
Quality
C.
Quality
Answers
D.
Progress
D.
Progress
Answers
Suggested answer: C

Explanation:

The Quality theme in PRINCE2 verifies that a project's products are fit for purpose. This theme ensures that the project delivers products that meet the requirements and standards necessary for acceptance by the customer and stakeholders, effectively supporting the achievement of the desired benefits.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which are benefits of using PRINCE2?

1. It removes the need for activity-based planning

2. It promotes learning and continuous improvement

3. It can be applied to any type of project

4. It defines specific leadership and other interpersonal skills required

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

The benefits of using PRINCE2 include promoting learning and continuous improvement, and its ability to be applied to any type of project. PRINCE2 provides a flexible methodology that encourages iterative learning from both current and past projects while being adaptable to various industries and project sizes.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which process provides information for the project board to review a completed stage and confirm continued business justification?

A.
Controlling a stage
A.
Controlling a stage
Answers
B.
Closing a project
B.
Closing a project
Answers
C.
Directing a project
C.
Directing a project
Answers
D.
Managing a stage boundary
D.
Managing a stage boundary
Answers
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 is designed to provide the project board with information to review the performance of a completed stage, confirm the continued business justification, and decide whether to proceed with the next stage. This process includes preparing key documents such as the End Stage Report and the next Stage Plan.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.

Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: A

Explanation:

The advantages of having a clear end to a project include ensuring that no further costs are incurred by the project (1) and that project products are transferred to operations and support for ongoing use (2). The achievement of all benefits at project closure (3) is not guaranteed and typically occurs post-project, and the project brief is not re-baselined at project end (4).

Reference: PRINCE2 Foundation Handbook, Closing a Project section.

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

A.
when a stage plan has been prepared for
A.
when a stage plan has been prepared for
Answers
B.
at the beginning of
B.
at the beginning of
Answers
C.
when all the delivery steps have been completed within
C.
when all the delivery steps have been completed within
Answers
D.
at, or close to the end of,
D.
at, or close to the end of,
Answers
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 should be executed at, or close to the end of, a management stage. This timing allows for proper assessment of the stage's outcomes and preparation for the next stage, ensuring effective planning and reporting as required by the project board.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.

The application of which principle helps to define what should be included in a project?

A.
Defined roles and responsibilities
A.
Defined roles and responsibilities
Answers
B.
Focus on products
B.
Focus on products
Answers
C.
Manage by stages
C.
Manage by stages
Answers
D.
Continued business justification
D.
Continued business justification
Answers
Suggested answer: D

Explanation:

The application of the 'Continued Business Justification' principle in PRINCE2 helps to define what should be included in a project. This principle ensures that a project remains viable and relevant, with a clear justification for starting and continuing each stage of the project. It supports decision-making about the inclusion of specific components or activities based on their contribution to project objectives and expected benefits.

Reference: PRINCE2 Foundation Handbook, Continued Business Justification section.

According to the 'continued business justification' principle, what must project benefits be aligned to?

A.
Regular deliveries throughout the project
A.
Regular deliveries throughout the project
Answers
B.
The business objectives
B.
The business objectives
Answers
C.
The direction of the project board
C.
The direction of the project board
Answers
D.
The technology available
D.
The technology available
Answers
Suggested answer: B

Explanation:

According to the 'continued business justification' principle in PRINCE2, project benefits must be aligned to the business objectives. This alignment ensures that the project remains viable and relevant throughout its life cycle, and that it contributes to achieving strategic goals.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Where should a team manager look for information about the quality required for a product?

A.
Project initiation documentation
A.
Project initiation documentation
Answers
B.
Product description
B.
Product description
Answers
C.
Team plan
C.
Team plan
Answers
D.
Quality management approach
D.
Quality management approach
Answers
Suggested answer: B

Explanation:

In PRINCE2, the information about the quality requirements for a product is detailed in the product description. This document specifies the quality criteria, quality methods, and the responsibilities for achieving the required quality.

Reference: PRINCE2 Foundation Handbook, Product Description section.