Question 181

Report
Export
Collapse

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Appointing the project board and producing the project brief
Appointing the project board and producing the project brief
Planning the initiation stage and appointing the project manager
Planning the initiation stage and appointing the project manager
Producing the additional role descriptions and validating the project product description
Producing the additional role descriptions and validating the project product description
Verifying the project approach and capturing previous lessons
Verifying the project approach and capturing previous lessons
Suggested answer: D

Explanation:

If a project is part of a programme, the activities related to verifying the project approach and capturing previous lessons in the 'Starting up a Project' process are most likely to be reduced or eliminated. This reduction occurs because the programme likely provides a strategic framework and lessons learned that the project can adopt directly.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Bert Pubben
38 questions

Question 182

Report
Export
Collapse

Which is part of quality control?

Undertaking quality reviews
Undertaking quality reviews
Writing product descriptions
Writing product descriptions
Providing assurance that the project is being conducted properly
Providing assurance that the project is being conducted properly
Documenting the customer's quality expectations
Documenting the customer's quality expectations
Suggested answer: A

Explanation:

Part of quality control within PRINCE2 involves undertaking quality reviews. These reviews are essential for ensuring that the project's outputs meet the required quality standards and are fit for purpose, aligning with the defined quality criteria set out in the product descriptions.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Shaun Kilmartin
26 questions

Question 183

Report
Export
Collapse

Which theme verifies that a project's products are fit for purpose?

Business case
Business case
Organization
Organization
Quality
Quality
Progress
Progress
Suggested answer: C

Explanation:

The Quality theme in PRINCE2 verifies that a project's products are fit for purpose. This theme ensures that the project delivers products that meet the requirements and standards necessary for acceptance by the customer and stakeholders, effectively supporting the achievement of the desired benefits.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
hajar mechrany
30 questions

Question 184

Report
Export
Collapse

Which are benefits of using PRINCE2?

1. It removes the need for activity-based planning

2. It promotes learning and continuous improvement

3. It can be applied to any type of project

4. It defines specific leadership and other interpersonal skills required

1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: B

Explanation:

The benefits of using PRINCE2 include promoting learning and continuous improvement, and its ability to be applied to any type of project. PRINCE2 provides a flexible methodology that encourages iterative learning from both current and past projects while being adaptable to various industries and project sizes.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Giulia Alberghi
43 questions

Question 185

Report
Export
Collapse

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Controlling a stage
Controlling a stage
Closing a project
Closing a project
Directing a project
Directing a project
Managing a stage boundary
Managing a stage boundary
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 is designed to provide the project board with information to review the performance of a completed stage, confirm the continued business justification, and decide whether to proceed with the next stage. This process includes preparing key documents such as the End Stage Report and the next Stage Plan.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.

asked 23/09/2024
Ana Rosa Abascal Ortega
39 questions

Question 186

Report
Export
Collapse

Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: A

Explanation:

The advantages of having a clear end to a project include ensuring that no further costs are incurred by the project (1) and that project products are transferred to operations and support for ongoing use (2). The achievement of all benefits at project closure (3) is not guaranteed and typically occurs post-project, and the project brief is not re-baselined at project end (4).

Reference: PRINCE2 Foundation Handbook, Closing a Project section.

asked 23/09/2024
Dave Breath
49 questions

Question 187

Report
Export
Collapse

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

when a stage plan has been prepared for
when a stage plan has been prepared for
at the beginning of
at the beginning of
when all the delivery steps have been completed within
when all the delivery steps have been completed within
at, or close to the end of,
at, or close to the end of,
Suggested answer: D

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 should be executed at, or close to the end of, a management stage. This timing allows for proper assessment of the stage's outcomes and preparation for the next stage, ensuring effective planning and reporting as required by the project board.

Reference: PRINCE2 Foundation Handbook, Managing a Stage Boundary section.

asked 23/09/2024
Feroz Khan
43 questions

Question 188

Report
Export
Collapse

The application of which principle helps to define what should be included in a project?

Defined roles and responsibilities
Defined roles and responsibilities
Focus on products
Focus on products
Manage by stages
Manage by stages
Continued business justification
Continued business justification
Suggested answer: D

Explanation:

The application of the 'Continued Business Justification' principle in PRINCE2 helps to define what should be included in a project. This principle ensures that a project remains viable and relevant, with a clear justification for starting and continuing each stage of the project. It supports decision-making about the inclusion of specific components or activities based on their contribution to project objectives and expected benefits.

Reference: PRINCE2 Foundation Handbook, Continued Business Justification section.

asked 23/09/2024
ajay jaiswal
37 questions

Question 189

Report
Export
Collapse

According to the 'continued business justification' principle, what must project benefits be aligned to?

Regular deliveries throughout the project
Regular deliveries throughout the project
The business objectives
The business objectives
The direction of the project board
The direction of the project board
The technology available
The technology available
Suggested answer: B

Explanation:

According to the 'continued business justification' principle in PRINCE2, project benefits must be aligned to the business objectives. This alignment ensures that the project remains viable and relevant throughout its life cycle, and that it contributes to achieving strategic goals.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Trey Contello
42 questions

Question 190

Report
Export
Collapse

Where should a team manager look for information about the quality required for a product?

Project initiation documentation
Project initiation documentation
Product description
Product description
Team plan
Team plan
Quality management approach
Quality management approach
Suggested answer: B

Explanation:

In PRINCE2, the information about the quality requirements for a product is detailed in the product description. This document specifies the quality criteria, quality methods, and the responsibilities for achieving the required quality.

Reference: PRINCE2 Foundation Handbook, Product Description section.