Question 201

Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
The purposes of the quality theme in PRINCE2 are to establish how the project will ensure that products are fit for purpose and meet stakeholder expectations (purpose 2) and to ensure that the project's objectives are desirable and achievable, which pertains to ensuring that the project has a solid business justification (purpose 3).
Reference: PRINCE2 Foundation Handbook, Quality Theme section.
Question 202

What is performed as part of the recommended risk management procedure?
As part of the recommended risk management procedure in PRINCE2, it is essential to regularly review risk management practices to ensure their effectiveness. This involves evaluating how risks are identified, assessed, and controlled throughout the project lifecycle.
Reference: PRINCE2 Foundation Handbook, Risk Management section.
Question 203

Within which integrated element does PRINCE2 set minimum requirements?
PRINCE2 sets minimum requirements within its themes. Themes support the principles and are aspects of project management that must be addressed continually and in parallel throughout the project. The themes provide knowledge areas necessary for the effective management of a project.
Reference: PRINCE2 Foundation Handbook, Themes section.
Question 204

Which is a purpose of the 'controlling a stage' process?
The purpose of the 'controlling a stage' process in PRINCE2 is to ensure that the stage stays on course and reacts to unexpected events. This includes taking corrective actions when there are deviations from the stage plan that can be managed within the tolerances set by the project board.
Reference: PRINCE2 Foundation Handbook, Controlling a Stage section.
Question 205

Which is a purpose of a project brief?
The purpose of a project brief in PRINCE2 is to provide a full and firm foundation for the initiation of the project. It includes information necessary to decide whether or not to initiate the project and acts as a base document against which the project board and key stakeholders can assess project progress during its lifecycle.
Reference: PRINCE2 Foundation Handbook, Project Brief section.
Question 206

Which role is responsible for the quality of the specialist products delivered in the project?
In PRINCE2, the Senior Supplier role is responsible for the quality of the specialist products delivered by the project. This role represents the interests of those designing, developing, facilitating, procuring, and implementing the project's products, ensuring that the products meet the required quality standards and fit for their intended purpose.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 207

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
The Risk Management Approach in PRINCE2 must include, at a minimum, a description of the risk management procedure. This description outlines how risks will be identified, assessed, and controlled throughout the project, ensuring that risk management is systematic and effective.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 208

Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
The missing word in the sentence is 'processes.' PRINCE2 is a method that addresses project management through four integrated elements: principles, themes, processes, and tailoring the method to suit the project environment. The processes component includes a series of steps and activities to be carried out during the project's lifecycle.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 209

Which is a minimum requirement for applying the change theme?
A minimum requirement for applying the Change Theme in PRINCE2 is to record every issue that is raised in the issue register. This ensures that all potential and actual deviations from the plan are captured and managed appropriately, maintaining control over changes and supporting effective decision-making.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 210

Why is the 'learn from experience' principle applied to a project?
The 'learn from experience' principle in PRINCE2 is applied to ensure that lessons are sought, recorded, and acted upon throughout the life of the project. This principle helps the project team to replicate successes and avoid repeating past mistakes, thereby improving the efficiency and effectiveness of the project.
Reference: PRINCE2 Foundation Handbook, Learn from Experience section.