Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

The purposes of the quality theme in PRINCE2 are to establish how the project will ensure that products are fit for purpose and meet stakeholder expectations (purpose 2) and to ensure that the project's objectives are desirable and achievable, which pertains to ensuring that the project has a solid business justification (purpose 3).

Reference: PRINCE2 Foundation Handbook, Quality Theme section.

What is performed as part of the recommended risk management procedure?

A.
A budget to investigate issues is allocated
A.
A budget to investigate issues is allocated
Answers
B.
Risk management practices are reviewed to ensure that they are performed effectively
B.
Risk management practices are reviewed to ensure that they are performed effectively
Answers
C.
Information about risks to the projects is sent to project stakeholders
C.
Information about risks to the projects is sent to project stakeholders
Answers
D.
Conflicts between the project and the programme board are resolved
D.
Conflicts between the project and the programme board are resolved
Answers
Suggested answer: B

Explanation:

As part of the recommended risk management procedure in PRINCE2, it is essential to regularly review risk management practices to ensure their effectiveness. This involves evaluating how risks are identified, assessed, and controlled throughout the project lifecycle.

Reference: PRINCE2 Foundation Handbook, Risk Management section.

Within which integrated element does PRINCE2 set minimum requirements?

A.
Themes
A.
Themes
Answers
B.
Processes
B.
Processes
Answers
C.
Principles
C.
Principles
Answers
D.
Project environment
D.
Project environment
Answers
Suggested answer: A

Explanation:

PRINCE2 sets minimum requirements within its themes. Themes support the principles and are aspects of project management that must be addressed continually and in parallel throughout the project. The themes provide knowledge areas necessary for the effective management of a project.

Reference: PRINCE2 Foundation Handbook, Themes section.

Which is a purpose of the 'controlling a stage' process?

A.
To produce a team plan for the work to be assigned to a team manager
A.
To produce a team plan for the work to be assigned to a team manager
Answers
B.
To select and implement actions that will resolve deviations from a plan within tolerance
B.
To select and implement actions that will resolve deviations from a plan within tolerance
Answers
C.
To obtain approvals for products delivered in a work package
C.
To obtain approvals for products delivered in a work package
Answers
D.
To update a project plan to incorporate the actuals from a stage plan
D.
To update a project plan to incorporate the actuals from a stage plan
Answers
Suggested answer: B

Explanation:

The purpose of the 'controlling a stage' process in PRINCE2 is to ensure that the stage stays on course and reacts to unexpected events. This includes taking corrective actions when there are deviations from the stage plan that can be managed within the tolerances set by the project board.

Reference: PRINCE2 Foundation Handbook, Controlling a Stage section.

Which is a purpose of a project brief?

A.
To act as a base document which enables the project board to assess progress
A.
To act as a base document which enables the project board to assess progress
Answers
B.
To provide a sound basis for project initiation
B.
To provide a sound basis for project initiation
Answers
C.
To define how the achievement of the project's benefits can be measured
C.
To define how the achievement of the project's benefits can be measured
Answers
D.
To provide a description of the means and frequency of communication
D.
To provide a description of the means and frequency of communication
Answers
Suggested answer: B

Explanation:

The purpose of a project brief in PRINCE2 is to provide a full and firm foundation for the initiation of the project. It includes information necessary to decide whether or not to initiate the project and acts as a base document against which the project board and key stakeholders can assess project progress during its lifecycle.

Reference: PRINCE2 Foundation Handbook, Project Brief section.

Which role is responsible for the quality of the specialist products delivered in the project?

A.
Executive
A.
Executive
Answers
B.
Senior user
B.
Senior user
Answers
C.
Senior supplier
C.
Senior supplier
Answers
D.
Project assurance
D.
Project assurance
Answers
Suggested answer: C

Explanation:

In PRINCE2, the Senior Supplier role is responsible for the quality of the specialist products delivered by the project. This role represents the interests of those designing, developing, facilitating, procuring, and implementing the project's products, ensuring that the products meet the required quality standards and fit for their intended purpose.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

A.
A description of the risk management procedure
A.
A description of the risk management procedure
Answers
B.
An explanation of the company's risk appetite
B.
An explanation of the company's risk appetite
Answers
C.
The names of the assigned actionees for each risk
C.
The names of the assigned actionees for each risk
Answers
D.
Estimations of the likelihood and impact of risks
D.
Estimations of the likelihood and impact of risks
Answers
Suggested answer: A

Explanation:

The Risk Management Approach in PRINCE2 must include, at a minimum, a description of the risk management procedure. This description outlines how risks will be identified, assessed, and controlled throughout the project, ensuring that risk management is systematic and effective.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

A.
activities
A.
activities
Answers
B.
processes
B.
processes
Answers
C.
products
C.
products
Answers
D.
quality
D.
quality
Answers
Suggested answer: B

Explanation:

The missing word in the sentence is 'processes.' PRINCE2 is a method that addresses project management through four integrated elements: principles, themes, processes, and tailoring the method to suit the project environment. The processes component includes a series of steps and activities to be carried out during the project's lifecycle.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is a minimum requirement for applying the change theme?

A.
To establish a change budget to fund changes in scope
A.
To establish a change budget to fund changes in scope
Answers
B.
To appoint the project manager as part of the change authority
B.
To appoint the project manager as part of the change authority
Answers
C.
To define the project's approach to baselining products
C.
To define the project's approach to baselining products
Answers
D.
To record every issue that is raised in the issue register
D.
To record every issue that is raised in the issue register
Answers
Suggested answer: D

Explanation:

A minimum requirement for applying the Change Theme in PRINCE2 is to record every issue that is raised in the issue register. This ensures that all potential and actual deviations from the plan are captured and managed appropriately, maintaining control over changes and supporting effective decision-making.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Why is the 'learn from experience' principle applied to a project?

A.
To enable the project team to repeat successes from previous projects
A.
To enable the project team to repeat successes from previous projects
Answers
B.
To enable the project team to develop a business case for the project
B.
To enable the project team to develop a business case for the project
Answers
C.
To allow the project to be divided into management stages
C.
To allow the project to be divided into management stages
Answers
D.
To enable the project team to use tolerances to delegate authority
D.
To enable the project team to use tolerances to delegate authority
Answers
Suggested answer: A

Explanation:

The 'learn from experience' principle in PRINCE2 is applied to ensure that lessons are sought, recorded, and acted upon throughout the life of the project. This principle helps the project team to replicate successes and avoid repeating past mistakes, thereby improving the efficiency and effectiveness of the project.

Reference: PRINCE2 Foundation Handbook, Learn from Experience section.