What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

The 'managing product delivery' process in PRINCE2 ensures that the planned products meet their quality criteria (ensuring products are fit for purpose) and that these products are delivered within the agreed tolerances (ensuring delivery within time, cost, quality, scope, risk, and benefit tolerances).

Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

A.
That the appropriate number and type of meetings are held
A.
That the appropriate number and type of meetings are held
Answers
B.
That the project is divided into an appropriate number of stages
B.
That the project is divided into an appropriate number of stages
Answers
C.
That the appropriate information is provided to make decisions
C.
That the appropriate information is provided to make decisions
Answers
D.
That the project method relates to the project's environment
D.
That the project method relates to the project's environment
Answers
Suggested answer: D

Explanation:

According to the 'tailor to suit the project' principle in PRINCE2, effective project management is based on adapting the method to suit the project's environment. This means the approach to managing the project should be appropriate to the specific circumstances of the project, including its scale, complexity, importance, capability, and risk.

Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

A.
Continued business justification
A.
Continued business justification
Answers
B.
Defined roles and responsibilities
B.
Defined roles and responsibilities
Answers
C.
Manage by exception
C.
Manage by exception
Answers
D.
Manage by stages
D.
Manage by stages
Answers
Suggested answer: C

Explanation:

The principle of 'manage by exception' in PRINCE2 involves setting tolerances for each project objective to establish clear limits of delegated authority. This allows for efficient use of management time and enables project managers to make decisions within the tolerance limits, while escalating issues that go beyond these limits.

Reference: PRINCE2 Foundation Handbook, Manage by Exception section.

Which describes an off-specification?

A.
An interdependency between products that was previously unidentified
A.
An interdependency between products that was previously unidentified
Answers
B.
The addition of an improvement to a product description
B.
The addition of an improvement to a product description
Answers
C.
A prototype demonstrating a possible design solution
C.
A prototype demonstrating a possible design solution
Answers
D.
The production of more than the defined quantity of a specialist product
D.
The production of more than the defined quantity of a specialist product
Answers
E.
That the right people are involved in appropriate roles
E.
That the right people are involved in appropriate roles
Answers
Suggested answer: D

Explanation:

An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or fails to deliver within the set tolerance levels. This could involve producing more or less of a product than was specified, or any other deviation from the product's agreed-upon specifications.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

A.
Creating a product flow diagram
A.
Creating a product flow diagram
Answers
B.
Writing the product description
B.
Writing the product description
Answers
C.
Writing a project product description
C.
Writing a project product description
Answers
D.
Documenting the plan
D.
Documenting the plan
Answers
Suggested answer: C

Explanation:

The first task in PRINCE2's recommended approach to 'defining and analyzing the products' is writing the Project Product Description. This document outlines what the project must deliver in order to gain acceptance. It serves as the basis for defining and analyzing more detailed product descriptions later in the process.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is an objective of the 'starting up a project' process?

A.
To approve the initiation stage
A.
To approve the initiation stage
Answers
B.
To select the project mandate
B.
To select the project mandate
Answers
C.
To define the project quality management approach
C.
To define the project quality management approach
Answers
D.
To appoint the project management team
D.
To appoint the project management team
Answers
Suggested answer: D

Explanation:

One of the objectives of the 'Starting up a Project' process in PRINCE2 is to appoint the project management team. This step ensures that the necessary leadership and management roles are filled with competent individuals who can plan, oversee, and execute the project effectively from its initiation through to closure.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

A.
Directing a project
A.
Directing a project
Answers
B.
Managing product delivery
B.
Managing product delivery
Answers
C.
Managing a stage boundary
C.
Managing a stage boundary
Answers
D.
Initiating a project
D.
Initiating a project
Answers
Suggested answer: B

Explanation:

The process that links the Team Manager role with the PRINCE2 method in a commercial environment is 'Managing Product Delivery'. This process ensures that the project's products are created and delivered efficiently and effectively, aligning the work of the team with the overall project management approach.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

A.
Manage by stages
A.
Manage by stages
Answers
B.
Manage by exception
B.
Manage by exception
Answers
C.
Continued business justification
C.
Continued business justification
Answers
D.
Learn from experience
D.
Learn from experience
Answers
Suggested answer: B

Explanation:

Setting tolerances for the three levels of plan (project, stage, and team) in PRINCE2 applies the principle of 'manage by exception'. This principle enables efficient use of management time by focusing on deviations from the plan only if they exceed predefined tolerances, rather than managing every small detail.

Reference: PRINCE2 Foundation Handbook, Manage by Exception section.

When should the level of tailoring be defined?

A.
During the initiation stage
A.
During the initiation stage
Answers
B.
When reviewing what has been learned to date
B.
When reviewing what has been learned to date
Answers
C.
As a response to issues and risks experienced
C.
As a response to issues and risks experienced
Answers
D.
Before the project is triggered by the project mandate
D.
Before the project is triggered by the project mandate
Answers
Suggested answer: A

Explanation:

The level of tailoring in PRINCE2 should be defined during the initiation stage of the project. This stage involves setting up the proper foundation for the project by adapting the method to suit the project's environment, including deciding how much and which parts of the methodology to apply.

Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.

Which is an objective of the 'initiating a project' process?

A.
To ensure that baselines are established and controlled
A.
To ensure that baselines are established and controlled
Answers
B.
To ensure that the business case is kept under review
B.
To ensure that the business case is kept under review
Answers
C.
To ensure that the planned products are delivered within tolerances
C.
To ensure that the planned products are delivered within tolerances
Answers
D.
To ensure that user acceptance of the products is confirmed
D.
To ensure that user acceptance of the products is confirmed
Answers
Suggested answer: B

Explanation:

An objective of the 'initiating a project' process in PRINCE2 is to ensure that the business case is kept under review. This involves establishing mechanisms to assess the ongoing viability of the project against its objectives and expected benefits.

Reference: PRINCE2 Foundation Handbook, Initiating a Project section.