Question 211

Report
Export
Collapse

What should the 'managing product delivery' process ensure?

1. That the planned products meet their quality criteria

2. That the stage plan is kept up to date

3. That the project board is provided with progress information

4. That the planned products are delivered within tolerance

1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: D

Explanation:

The 'managing product delivery' process in PRINCE2 ensures that the planned products meet their quality criteria (ensuring products are fit for purpose) and that these products are delivered within the agreed tolerances (ensuring delivery within time, cost, quality, scope, risk, and benefit tolerances).

Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.

asked 23/09/2024
Szymon Strzep
39 questions

Question 212

Report
Export
Collapse

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

That the appropriate number and type of meetings are held
That the appropriate number and type of meetings are held
That the project is divided into an appropriate number of stages
That the project is divided into an appropriate number of stages
That the appropriate information is provided to make decisions
That the appropriate information is provided to make decisions
That the project method relates to the project's environment
That the project method relates to the project's environment
Suggested answer: D

Explanation:

According to the 'tailor to suit the project' principle in PRINCE2, effective project management is based on adapting the method to suit the project's environment. This means the approach to managing the project should be appropriate to the specific circumstances of the project, including its scale, complexity, importance, capability, and risk.

Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.

asked 23/09/2024
Srikar Gude
31 questions

Question 213

Report
Export
Collapse

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

Continued business justification
Continued business justification
Defined roles and responsibilities
Defined roles and responsibilities
Manage by exception
Manage by exception
Manage by stages
Manage by stages
Suggested answer: C

Explanation:

The principle of 'manage by exception' in PRINCE2 involves setting tolerances for each project objective to establish clear limits of delegated authority. This allows for efficient use of management time and enables project managers to make decisions within the tolerance limits, while escalating issues that go beyond these limits.

Reference: PRINCE2 Foundation Handbook, Manage by Exception section.

asked 23/09/2024
Shariifa DEME
33 questions

Question 214

Report
Export
Collapse

Which describes an off-specification?

An interdependency between products that was previously unidentified
An interdependency between products that was previously unidentified
The addition of an improvement to a product description
The addition of an improvement to a product description
A prototype demonstrating a possible design solution
A prototype demonstrating a possible design solution
The production of more than the defined quantity of a specialist product
The production of more than the defined quantity of a specialist product
That the right people are involved in appropriate roles
That the right people are involved in appropriate roles
Suggested answer: D

Explanation:

An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or fails to deliver within the set tolerance levels. This could involve producing more or less of a product than was specified, or any other deviation from the product's agreed-upon specifications.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
francesca parisi
25 questions

Question 215

Report
Export
Collapse

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

Creating a product flow diagram
Creating a product flow diagram
Writing the product description
Writing the product description
Writing a project product description
Writing a project product description
Documenting the plan
Documenting the plan
Suggested answer: C

Explanation:

The first task in PRINCE2's recommended approach to 'defining and analyzing the products' is writing the Project Product Description. This document outlines what the project must deliver in order to gain acceptance. It serves as the basis for defining and analyzing more detailed product descriptions later in the process.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Coleman Owie
39 questions

Question 216

Report
Export
Collapse

Which is an objective of the 'starting up a project' process?

To approve the initiation stage
To approve the initiation stage
To select the project mandate
To select the project mandate
To define the project quality management approach
To define the project quality management approach
To appoint the project management team
To appoint the project management team
Suggested answer: D

Explanation:

One of the objectives of the 'Starting up a Project' process in PRINCE2 is to appoint the project management team. This step ensures that the necessary leadership and management roles are filled with competent individuals who can plan, oversee, and execute the project effectively from its initiation through to closure.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Anu V
34 questions

Question 217

Report
Export
Collapse

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

Directing a project
Directing a project
Managing product delivery
Managing product delivery
Managing a stage boundary
Managing a stage boundary
Initiating a project
Initiating a project
Suggested answer: B

Explanation:

The process that links the Team Manager role with the PRINCE2 method in a commercial environment is 'Managing Product Delivery'. This process ensures that the project's products are created and delivered efficiently and effectively, aligning the work of the team with the overall project management approach.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Thembinkosi Sibiya
34 questions

Question 218

Report
Export
Collapse

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

Manage by stages
Manage by stages
Manage by exception
Manage by exception
Continued business justification
Continued business justification
Learn from experience
Learn from experience
Suggested answer: B

Explanation:

Setting tolerances for the three levels of plan (project, stage, and team) in PRINCE2 applies the principle of 'manage by exception'. This principle enables efficient use of management time by focusing on deviations from the plan only if they exceed predefined tolerances, rather than managing every small detail.

Reference: PRINCE2 Foundation Handbook, Manage by Exception section.

asked 23/09/2024
Jana Rutrich
29 questions

Question 219

Report
Export
Collapse

When should the level of tailoring be defined?

During the initiation stage
During the initiation stage
When reviewing what has been learned to date
When reviewing what has been learned to date
As a response to issues and risks experienced
As a response to issues and risks experienced
Before the project is triggered by the project mandate
Before the project is triggered by the project mandate
Suggested answer: A

Explanation:

The level of tailoring in PRINCE2 should be defined during the initiation stage of the project. This stage involves setting up the proper foundation for the project by adapting the method to suit the project's environment, including deciding how much and which parts of the methodology to apply.

Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.

asked 23/09/2024
Hristo Slaveev
25 questions

Question 220

Report
Export
Collapse

Which is an objective of the 'initiating a project' process?

To ensure that baselines are established and controlled
To ensure that baselines are established and controlled
To ensure that the business case is kept under review
To ensure that the business case is kept under review
To ensure that the planned products are delivered within tolerances
To ensure that the planned products are delivered within tolerances
To ensure that user acceptance of the products is confirmed
To ensure that user acceptance of the products is confirmed
Suggested answer: B

Explanation:

An objective of the 'initiating a project' process in PRINCE2 is to ensure that the business case is kept under review. This involves establishing mechanisms to assess the ongoing viability of the project against its objectives and expected benefits.

Reference: PRINCE2 Foundation Handbook, Initiating a Project section.

asked 23/09/2024
Juan Contreras
36 questions
Total 463 questions