Question 211

What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
Explanation:
The 'managing product delivery' process in PRINCE2 ensures that the planned products meet their quality criteria (ensuring products are fit for purpose) and that these products are delivered within the agreed tolerances (ensuring delivery within time, cost, quality, scope, risk, and benefit tolerances).
Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.
Question 212

According to the 'tailor to suit the project' principle, what is the basis for effective project management?
Explanation:
According to the 'tailor to suit the project' principle in PRINCE2, effective project management is based on adapting the method to suit the project's environment. This means the approach to managing the project should be appropriate to the specific circumstances of the project, including its scale, complexity, importance, capability, and risk.
Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.
Question 213

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
Explanation:
The principle of 'manage by exception' in PRINCE2 involves setting tolerances for each project objective to establish clear limits of delegated authority. This allows for efficient use of management time and enables project managers to make decisions within the tolerance limits, while escalating issues that go beyond these limits.
Reference: PRINCE2 Foundation Handbook, Manage by Exception section.
Question 214

Which describes an off-specification?
Explanation:
An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or fails to deliver within the set tolerance levels. This could involve producing more or less of a product than was specified, or any other deviation from the product's agreed-upon specifications.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 215

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
Explanation:
The first task in PRINCE2's recommended approach to 'defining and analyzing the products' is writing the Project Product Description. This document outlines what the project must deliver in order to gain acceptance. It serves as the basis for defining and analyzing more detailed product descriptions later in the process.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 216

Which is an objective of the 'starting up a project' process?
Explanation:
One of the objectives of the 'Starting up a Project' process in PRINCE2 is to appoint the project management team. This step ensures that the necessary leadership and management roles are filled with competent individuals who can plan, oversee, and execute the project effectively from its initiation through to closure.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 217

In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
Explanation:
The process that links the Team Manager role with the PRINCE2 method in a commercial environment is 'Managing Product Delivery'. This process ensures that the project's products are created and delivered efficiently and effectively, aligning the work of the team with the overall project management approach.
Reference: PRINCE2 7 Foundation Handbook and official training materials.
Question 218

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
Explanation:
Setting tolerances for the three levels of plan (project, stage, and team) in PRINCE2 applies the principle of 'manage by exception'. This principle enables efficient use of management time by focusing on deviations from the plan only if they exceed predefined tolerances, rather than managing every small detail.
Reference: PRINCE2 Foundation Handbook, Manage by Exception section.
Question 219

When should the level of tailoring be defined?
Explanation:
The level of tailoring in PRINCE2 should be defined during the initiation stage of the project. This stage involves setting up the proper foundation for the project by adapting the method to suit the project's environment, including deciding how much and which parts of the methodology to apply.
Reference: PRINCE2 Foundation Handbook, Tailoring PRINCE2 section.
Question 220

Which is an objective of the 'initiating a project' process?
Explanation:
An objective of the 'initiating a project' process in PRINCE2 is to ensure that the business case is kept under review. This involves establishing mechanisms to assess the ongoing viability of the project against its objectives and expected benefits.
Reference: PRINCE2 Foundation Handbook, Initiating a Project section.