Which is a purpose of the 'closing a project' process?

A.
To provide the project board with information to judge the success of a stage
A.
To provide the project board with information to judge the success of a stage
Answers
B.
To confirm the project has nothing more to deliver
B.
To confirm the project has nothing more to deliver
Answers
C.
To establish mechanisms to judge whether the project is still viable
C.
To establish mechanisms to judge whether the project is still viable
Answers
D.
To establish mechanisms for forecasting project objectives
D.
To establish mechanisms for forecasting project objectives
Answers
Suggested answer: B

Explanation:

The purpose of the 'closing a project' process in PRINCE2 is to verify that all project objectives have been delivered and that the project has nothing more to deliver. It ensures that all project products have been handed over and accepted, and evaluates the performance of the project against its baselines.

Reference: PRINCE2 Foundation Handbook, Closing a Project Process section.

Which is a purpose of a lessons log?

A.
To record any lessons that are raised in checkpoint reports
A.
To record any lessons that are raised in checkpoint reports
Answers
B.
To document that corrective action is being taken
B.
To document that corrective action is being taken
Answers
C.
To escalate lessons to the project board
C.
To escalate lessons to the project board
Answers
D.
To raise improvements with project assurance
D.
To raise improvements with project assurance
Answers
Suggested answer: A

Explanation:

The lessons log in PRINCE2 is used to record any lessons that can potentially improve future projects or stages. These lessons often originate from experiences documented in checkpoint reports, among other sources.

Reference: PRINCE2 Foundation Handbook, Lessons Log section.

Which are characteristics of stakeholders?

1. They are often affected by the project

2. They agree with every project objective

3. They are only/always external to the corporate organization

4. They typically interact with the project

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

Stakeholders in PRINCE2 are typically characterized by being affected by the project (either through impact or interest) and frequently interacting with the project, contributing inputs or being consulted for various aspects. This recognizes stakeholders as both internal and external to the organization, and not all stakeholders necessarily agree with every project objective.

Reference: PRINCE2 Foundation Handbook, Stakeholder section.

Which role represents the stakeholders who will operate the project's products after the project is complete?

A.
Executive
A.
Executive
Answers
B.
Senior user
B.
Senior user
Answers
C.
Senior supplier
C.
Senior supplier
Answers
D.
Project manager
D.
Project manager
Answers
Suggested answer: B

Explanation:

In PRINCE2, the Senior User role represents the interests of those who will use the project's products, those for whom the products will enable benefits after the project is complete, and any others who might be affected by the project outputs. This role is essential in ensuring that the project delivers products that meet the users' needs and achieve the desired benefits for the organization.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

A.
Manage by exception
A.
Manage by exception
Answers
B.
Learn from experience
B.
Learn from experience
Answers
C.
Tailor to suit the project environment
C.
Tailor to suit the project environment
Answers
D.
Defined roles and responsibilities
D.
Defined roles and responsibilities
Answers
Suggested answer: D

Explanation:

The PRINCE2 principle of 'Defined roles and responsibilities' is crucial because it establishes a clear understanding of who is involved in the project and what each member of the team is expected to do. This clarity ensures that everyone knows their specific responsibilities, contributing to effective project governance and smooth execution.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is a minimum requirement for applying the organization theme?

A.
Each member of the project management team must have a written role description
A.
Each member of the project management team must have a written role description
Answers
B.
The roles of the project management team must be combined, wherever possible
B.
The roles of the project management team must be combined, wherever possible
Answers
C.
The project manager must be appointed from the supplier organization
C.
The project manager must be appointed from the supplier organization
Answers
D.
The frequency of communication to the project's stakeholders must be documented
D.
The frequency of communication to the project's stakeholders must be documented
Answers
Suggested answer: A

Explanation:

According to the PRINCE2 methodology, a key requirement for applying the organization theme is ensuring that each member of the project management team has a clear and written role description. This document outlines their duties, responsibilities, and relationships to other roles within the project, which is fundamental for organizational clarity and accountability.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which statement about time-driven controls is CORRECT?

A.
Time-driven controls are used for monitoring the progress of work packages and management stages
A.
Time-driven controls are used for monitoring the progress of work packages and management stages
Answers
B.
Time-driven controls take place when specific events happen
B.
Time-driven controls take place when specific events happen
Answers
C.
Time-driven controls are produced at the end of a stage
C.
Time-driven controls are produced at the end of a stage
Answers
D.
An exception report is a time-driven control
D.
An exception report is a time-driven control
Answers
Suggested answer: A

Explanation:

Time-driven controls in PRINCE2 are mechanisms that take place at predetermined intervals, such as end stage assessments or regular progress meetings, to ensure ongoing monitoring of the project's progression through its stages and the work being completed in work packages. They help in keeping the project on track by providing timely information on performance.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

How does the project plan help to support the 'manage by stages' principle?

A.
By identifying the customer's quality expectations
A.
By identifying the customer's quality expectations
Answers
B.
By defining products to ensure they are fit for purpose
B.
By defining products to ensure they are fit for purpose
Answers
C.
By identifying the major control points and milestones
C.
By identifying the major control points and milestones
Answers
D.
By estimating the timescales and costs of the project
D.
By estimating the timescales and costs of the project
Answers
Suggested answer: C

Explanation:

The project plan supports the 'manage by stages' principle in PRINCE2 by identifying major control points and milestones. These serve as points at which the project board can review progress and decide whether to continue with the project. This principle ensures that the project is manageable, controllable, and that decisions can be made with proper governance at each stage.

Reference: PRINCE2 Foundation Handbook, Manage by Stages section.

Which is a purpose of the 'managing a stage boundary' process?

A.
To enable the project board to approve the continuation of the project
A.
To enable the project board to approve the continuation of the project
Answers
B.
To exercise overall control over the project while delegating day-to-day management
B.
To exercise overall control over the project while delegating day-to-day management
Answers
C.
To assign work to be controlled by the team manager
C.
To assign work to be controlled by the team manager
Answers
D.
To define the work that needs to be done to deliver the project product
D.
To define the work that needs to be done to deliver the project product
Answers
Suggested answer: A

Explanation:

The purpose of the 'Managing a Stage Boundary' process in PRINCE2 is to prepare the next stage plan and provide the project board with key information needed to make a decision on whether to continue with the project. This process involves reviewing the current stage's progress and the overall project status to ensure project viability before moving forward.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which product identifies how often stakeholders require information?

A.
Communication management approach
A.
Communication management approach
Answers
B.
Quality management approach
B.
Quality management approach
Answers
C.
Change control approach
C.
Change control approach
Answers
D.
Risk management approach
D.
Risk management approach
Answers
Suggested answer: A

Explanation:

The Communication Management Approach in PRINCE2 outlines the means and frequency of communication to stakeholders throughout the project. This document specifies how often stakeholders require updates and information regarding the project's progress and any issues that arise, ensuring that all parties are adequately informed.

Reference: PRINCE2 7 Foundation Handbook and official training materials.