Question 161

Report
Export
Collapse

Which is a purpose of a quality register?

To record the quality management approach for a product
To record the quality management approach for a product
To issue a unique reference number for each product
To issue a unique reference number for each product
To detail the number and type of quality activities to be conducted
To detail the number and type of quality activities to be conducted
To identify corrective actions that are required after an audit by quality assurance
To identify corrective actions that are required after an audit by quality assurance
Suggested answer: C

Explanation:

The purpose of a Quality Register in PRINCE2 is to detail the number and type of quality activities to be conducted. This register records all planned and completed quality activities, including details about each quality check, such as who will perform it, when, and with what result. This helps ensure all required quality reviews, tests, and evaluations are organized and tracked throughout the project.

Reference: PRINCE2 7 Foundation resources and study materials.

asked 23/09/2024
Mirza Daniyal Baig
40 questions

Question 162

Report
Export
Collapse

Which describes a characteristic of a project?

It maintains business as usual profitability
It maintains business as usual profitability
It provides a quality service to customers
It provides a quality service to customers
It involves a team with different skills
It involves a team with different skills
It enables established and proven best practices
It enables established and proven best practices
Suggested answer: C

Explanation:

A characteristic of a project is that it involves a team with different skills. Projects typically require a combination of various skills and expertise to deliver the project's products. This collaboration of diverse skills sets projects apart from regular, routine business activities, which may not require such varied expertise.

Reference: PRINCE2 7 Foundation handbook and documents.

asked 23/09/2024
Sanaa CHOKIRI
45 questions

Question 163

Report
Export
Collapse

What is the project manager role responsible for?

Approving the completion of each management stage
Approving the completion of each management stage
Ensuring that the project produces the required products
Ensuring that the project produces the required products
Defining the project-level tolerances
Defining the project-level tolerances
Verifying that the project gives value for money
Verifying that the project gives value for money
Suggested answer: B

Explanation:

The Project Manager role in PRINCE2 is primarily responsible for ensuring that the project produces the required products, to the defined standards of quality and within the specified constraints of time and cost. This central responsibility involves coordinating all project activities and resources to achieve the project objectives.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
OLUWAGBENRO AFUWAPE
39 questions

Question 164

Report
Export
Collapse

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Progress
Progress
Change
Change
Organization
Organization
Quality
Quality
Suggested answer: A

Explanation:

The Progress theme provides all management levels within the project management team with mechanisms for monitoring and control. This theme ensures that there are clear benchmarks for performance and mechanisms in place to assess progress throughout the project's life cycle.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Jérémy FRAISSENET
33 questions

Question 165

Report
Export
Collapse

Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Directing a project
Directing a project
Managing a stage boundary
Managing a stage boundary
Controlling a stage
Controlling a stage
Starting up a project
Starting up a project
Suggested answer: C

Explanation:

The Controlling a Stage process ensures focus on the delivery of a stage's products and helps avoid uncontrolled change by managing by exception, authorizing work packages, and monitoring the stage's progress against its plan.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Yrae Franca de Pinho Gomes
50 questions

Question 166

Report
Export
Collapse

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

Project mandate
Project mandate
Initiation stage plan
Initiation stage plan
Project initiation documentation
Project initiation documentation
Project brief
Project brief
Suggested answer: D

Explanation:

The Project Brief is created during the Starting up a Project process. It defines and confirms the scope of the project, providing a foundation for the Initiation Stage and ensuring that all project stakeholders have a clear understanding of the project's objectives and scope.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Kabi Bashala
36 questions

Question 167

Report
Export
Collapse

Which is a minimum requirement for applying the quality theme?

To use lessons to inform quality planning
To use lessons to inform quality planning
To use the prescribed approach to quality management
To use the prescribed approach to quality management
To use external quality standards for quality control
To use external quality standards for quality control
To use user stories to inform the project product description
To use user stories to inform the project product description
Suggested answer: A

Explanation:

A minimum requirement for applying the Quality theme is to use lessons learned to inform quality planning. This ensures that insights gained from past projects or earlier phases of the current project are used to improve quality management practices throughout the project's lifecycle.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Leandra Felipe
38 questions

Question 168

Report
Export
Collapse

Identify the missing words in the following sentence.

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

the 'starting up a project' process is completed
the 'starting up a project' process is completed
the project mandate has been approved by the project board
the project mandate has been approved by the project board
the project board has agreed the project strategies
the project board has agreed the project strategies
corporate, programme management or the customer have authorized a project
corporate, programme management or the customer have authorized a project
Suggested answer: A

Explanation:

The 'Directing a Project' process in PRINCE2 starts when the 'Starting up a Project' process is completed. This transition is triggered by the request to initiate a project. At this point, the project has been preliminarily assessed, and a project brief and initiation documentation are ready to be developed during the 'Initiating a Project' process, pending authorization from the Project Board to proceed.

Reference: PRINCE2 7 Foundation handbook and official documents.

asked 23/09/2024
TONG CHEE LOONG
35 questions

Question 169

Report
Export
Collapse

Which process is used to define how baselines will be established and controlled?

Controlling a stage
Controlling a stage
Directing a project
Directing a project
Initiating a project
Initiating a project
Starting up a project
Starting up a project
Suggested answer: C

Explanation:

The process used to define how baselines will be established and controlled is 'Initiating a Project'. During this process, the project's management strategies, including quality, risk, communication, and configuration management strategies, are defined. These strategies include how baselines for the project's products and plans will be established and controlled throughout the project lifecycle.

Reference: PRINCE2 7 Foundation resources and study materials.

asked 23/09/2024
Mohamed Ismail
49 questions

Question 170

Report
Export
Collapse

Which risk response is applied on a pain/gain basis?

Share
Share
Accept
Accept
Exploit
Exploit
Enhance
Enhance
Suggested answer: A

Explanation:

The risk response type that is applied on a pain/gain basis is 'Share'. Sharing involves partnering with others to share the impact of the risk. This is often used for both threats and opportunities where sharing the risk can enhance the capability to capitalize on the opportunity or mitigate the threat, with potential gains or savings being distributed according to an agreed formula.

Reference: PRINCE2 7 Foundation handbook and documents.