ExamGecko
Home / PRINCE2 / PRINCE2-7-Foundation
Ask Question

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 14

Question list
Search

Question 131

Report
Export
Collapse

Which is a purpose of the Risk theme?

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Establish a cost-effective procedure to identify, assess and control uncertainty
Establish a cost-effective procedure to identify, assess and control uncertainty
Establish mechanisms to control any unacceptable deviations from plan
Establish mechanisms to control any unacceptable deviations from plan
Establish mechanisms to manage risks at the corporate or programme level of an organization
Establish mechanisms to manage risks at the corporate or programme level of an organization
Suggested answer: B

Explanation:

The purpose of the Risk theme in PRINCE2 is to establish a cost-effective procedure to identify, assess, and control the uncertainties or risks that can affect the achievement of project objectives. This involves understanding how risks can impact the project and managing them proactively to ensure project success.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
samer salami
34 questions

Question 132

Report
Export
Collapse

Which is a factor when deciding the duration of a management stage?

The work packages to be delivered
The work packages to be delivered
The level of risk in the project
The level of risk in the project
The cost of the stage
The cost of the stage
The number of products to be produced in the project
The number of products to be produced in the project
Suggested answer: A

Explanation:

When deciding the duration of a management stage in PRINCE2, one key factor is the work packages to be delivered during the stage. The content and complexity of these work packages can significantly influence the length of the stage, as they define the scope and volume of work to be completed before the next stage review.

Reference: PRINCE2 Foundation Handbook, Tailoring and Adopting PRINCE2 section.

asked 23/09/2024
safiqueahmed kazi
37 questions

Question 133

Report
Export
Collapse

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

The senior user's responsibilities for realizing benefits
The senior user's responsibilities for realizing benefits
Statements of actual versus forecast benefits at reviews
Statements of actual versus forecast benefits at reviews
The management actions needed to ensure benefits are realized
The management actions needed to ensure benefits are realized
No specific documents related to benefits are necessary
No specific documents related to benefits are necessary
Suggested answer: C

Explanation:

According to PRINCE2 principles, the business case theme requires documenting the management actions necessary to ensure benefits are realized. This involves planning, measuring, and managing the realization of benefits, and it's critical for maintaining the relevance and justification of the project.

Reference: PRINCE2 Foundation Handbook, Business Case Theme section.

asked 23/09/2024
Fabio Zannetti
36 questions

Question 134

Report
Export
Collapse

According to PRINCE2, why might there be more than one business case for a project?

There may be more than one management stage in the project
There may be more than one management stage in the project
The project may be in a commercial environment with a number of suppliers
The project may be in a commercial environment with a number of suppliers
There may be more than one work package being delivered in the project
There may be more than one work package being delivered in the project
The project may be in a programme environment
The project may be in a programme environment
Suggested answer: D

Explanation:

In a programme environment, there might be multiple business cases within a single project, each supporting different parts of the programme's overall goals. This scenario is common when a project is designed to deliver outputs that contribute to several overlapping strategies or objectives within the programme.

Reference: PRINCE2 Foundation Handbook, Business Case Theme section.

asked 23/09/2024
Arno Rodenhuis
49 questions

Question 135

Report
Export
Collapse

What is a benefits management approach used to assess?

How the project's products have performed when in operational use
How the project's products have performed when in operational use
The effectiveness of the project strategies
The effectiveness of the project strategies
How the project has progressed against its plans
How the project has progressed against its plans
The suitability of the project management team structure
The suitability of the project management team structure
Suggested answer: A

Explanation:

The Benefits Management Approach in PRINCE2 is a document that describes how and when a measurement of the achievement of the project's benefits, both during and after the project, can be made. It is used to assess the performance of the project's products once they are in operational use, ensuring that the project delivers the intended benefits as outlined in the Business Case.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Nghia To Duc
53 questions

Question 136

Report
Export
Collapse

Why is the 'initiating a project' process used?

To decide which project approach is suitable for the project
To decide which project approach is suitable for the project
To fully understand how the project objectives will be achieved before committing significant resources
To fully understand how the project objectives will be achieved before committing significant resources
To produce the required work packages
To produce the required work packages
To enable corporate or programme management to give authorization to deliver a project
To enable corporate or programme management to give authorization to deliver a project
Suggested answer: B

Explanation:

The 'Initiating a Project' process in PRINCE2 is crucial for establishing a solid foundation for the project. This process is used to ensure that there is a shared understanding of the reasons for undertaking the project, the way its objectives will be achieved, and the related commitments of time and resources before substantial resources are committed.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

asked 23/09/2024
Himal Rai
39 questions

Question 137

Report
Export
Collapse

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

change budget
change budget
project budget
project budget
project's cost tolerance
project's cost tolerance
project's risk tolerance
project's risk tolerance
Suggested answer: B

Explanation:

A risk budget is a specific amount of money set aside within the project budget to address potential threats and opportunities. This allocation is used to fund the specific management responses required to mitigate identified risks.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Johan Benavides
42 questions

Question 138

Report
Export
Collapse

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Risk category
Risk category
Risk description
Risk description
Risk response
Risk response
Risk status
Risk status
Suggested answer: C

Explanation:

Risk response refers to the actions identified and implemented to bring the risk exposure to an acceptable level. These actions are part of the risk management process and aim to reduce, avoid, transfer, or accept risks depending on their potential impact on the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Anthony Zaborski
48 questions

Question 139

Report
Export
Collapse

Which describes a risk effect?

The uncertainty expressed as a negative or favourable occurrence
The uncertainty expressed as a negative or favourable occurrence
The issue which is affecting the project and has resulted in a risk
The issue which is affecting the project and has resulted in a risk
The impact(s) on the project objectives should the threat or opportunity occur
The impact(s) on the project objectives should the threat or opportunity occur
The change in the status of a risk in response to actions taken to control it
The change in the status of a risk in response to actions taken to control it
Suggested answer: C

Explanation:

The risk effect in PRINCE2 describes the potential impact on project objectives if a specific threat or opportunity were to occur. This understanding is crucial in assessing the significance of the risk and determining the appropriate management response.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Barry Richards
30 questions

Question 140

Report
Export
Collapse

Which describes risk probability?

Level of risks which the project can tolerate before escalating to the Project Board
Level of risks which the project can tolerate before escalating to the Project Board
Probable effect on the project delivering its objectives
Probable effect on the project delivering its objectives
Timeframe within which the risk may occur
Timeframe within which the risk may occur
A measure of the likelihood of the risk occurring
A measure of the likelihood of the risk occurring
Suggested answer: D

Explanation:

Risk probability in PRINCE2 refers to the measure of the likelihood that a particular risk will occur. It is a fundamental aspect of risk assessment, influencing the prioritization and management of risks within the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Norman Camacho
47 questions
Total 463 questions
Go to page: of 47