ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 14

Question list
Search
Search

Which is a purpose of the Risk theme?

A.
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
A.
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Answers
B.
Establish a cost-effective procedure to identify, assess and control uncertainty
B.
Establish a cost-effective procedure to identify, assess and control uncertainty
Answers
C.
Establish mechanisms to control any unacceptable deviations from plan
C.
Establish mechanisms to control any unacceptable deviations from plan
Answers
D.
Establish mechanisms to manage risks at the corporate or programme level of an organization
D.
Establish mechanisms to manage risks at the corporate or programme level of an organization
Answers
Suggested answer: B

Explanation:

The purpose of the Risk theme in PRINCE2 is to establish a cost-effective procedure to identify, assess, and control the uncertainties or risks that can affect the achievement of project objectives. This involves understanding how risks can impact the project and managing them proactively to ensure project success.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is a factor when deciding the duration of a management stage?

A.
The work packages to be delivered
A.
The work packages to be delivered
Answers
B.
The level of risk in the project
B.
The level of risk in the project
Answers
C.
The cost of the stage
C.
The cost of the stage
Answers
D.
The number of products to be produced in the project
D.
The number of products to be produced in the project
Answers
Suggested answer: A

Explanation:

When deciding the duration of a management stage in PRINCE2, one key factor is the work packages to be delivered during the stage. The content and complexity of these work packages can significantly influence the length of the stage, as they define the scope and volume of work to be completed before the next stage review.

Reference: PRINCE2 Foundation Handbook, Tailoring and Adopting PRINCE2 section.

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

A.
The senior user's responsibilities for realizing benefits
A.
The senior user's responsibilities for realizing benefits
Answers
B.
Statements of actual versus forecast benefits at reviews
B.
Statements of actual versus forecast benefits at reviews
Answers
C.
The management actions needed to ensure benefits are realized
C.
The management actions needed to ensure benefits are realized
Answers
D.
No specific documents related to benefits are necessary
D.
No specific documents related to benefits are necessary
Answers
Suggested answer: C

Explanation:

According to PRINCE2 principles, the business case theme requires documenting the management actions necessary to ensure benefits are realized. This involves planning, measuring, and managing the realization of benefits, and it's critical for maintaining the relevance and justification of the project.

Reference: PRINCE2 Foundation Handbook, Business Case Theme section.

According to PRINCE2, why might there be more than one business case for a project?

A.
There may be more than one management stage in the project
A.
There may be more than one management stage in the project
Answers
B.
The project may be in a commercial environment with a number of suppliers
B.
The project may be in a commercial environment with a number of suppliers
Answers
C.
There may be more than one work package being delivered in the project
C.
There may be more than one work package being delivered in the project
Answers
D.
The project may be in a programme environment
D.
The project may be in a programme environment
Answers
Suggested answer: D

Explanation:

In a programme environment, there might be multiple business cases within a single project, each supporting different parts of the programme's overall goals. This scenario is common when a project is designed to deliver outputs that contribute to several overlapping strategies or objectives within the programme.

Reference: PRINCE2 Foundation Handbook, Business Case Theme section.

What is a benefits management approach used to assess?

A.
How the project's products have performed when in operational use
A.
How the project's products have performed when in operational use
Answers
B.
The effectiveness of the project strategies
B.
The effectiveness of the project strategies
Answers
C.
How the project has progressed against its plans
C.
How the project has progressed against its plans
Answers
D.
The suitability of the project management team structure
D.
The suitability of the project management team structure
Answers
Suggested answer: A

Explanation:

The Benefits Management Approach in PRINCE2 is a document that describes how and when a measurement of the achievement of the project's benefits, both during and after the project, can be made. It is used to assess the performance of the project's products once they are in operational use, ensuring that the project delivers the intended benefits as outlined in the Business Case.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Why is the 'initiating a project' process used?

A.
To decide which project approach is suitable for the project
A.
To decide which project approach is suitable for the project
Answers
B.
To fully understand how the project objectives will be achieved before committing significant resources
B.
To fully understand how the project objectives will be achieved before committing significant resources
Answers
C.
To produce the required work packages
C.
To produce the required work packages
Answers
D.
To enable corporate or programme management to give authorization to deliver a project
D.
To enable corporate or programme management to give authorization to deliver a project
Answers
Suggested answer: B

Explanation:

The 'Initiating a Project' process in PRINCE2 is crucial for establishing a solid foundation for the project. This process is used to ensure that there is a shared understanding of the reasons for undertaking the project, the way its objectives will be achieved, and the related commitments of time and resources before substantial resources are committed.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

A.
change budget
A.
change budget
Answers
B.
project budget
B.
project budget
Answers
C.
project's cost tolerance
C.
project's cost tolerance
Answers
D.
project's risk tolerance
D.
project's risk tolerance
Answers
Suggested answer: B

Explanation:

A risk budget is a specific amount of money set aside within the project budget to address potential threats and opportunities. This allocation is used to fund the specific management responses required to mitigate identified risks.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A.
Risk category
A.
Risk category
Answers
B.
Risk description
B.
Risk description
Answers
C.
Risk response
C.
Risk response
Answers
D.
Risk status
D.
Risk status
Answers
Suggested answer: C

Explanation:

Risk response refers to the actions identified and implemented to bring the risk exposure to an acceptable level. These actions are part of the risk management process and aim to reduce, avoid, transfer, or accept risks depending on their potential impact on the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which describes a risk effect?

A.
The uncertainty expressed as a negative or favourable occurrence
A.
The uncertainty expressed as a negative or favourable occurrence
Answers
B.
The issue which is affecting the project and has resulted in a risk
B.
The issue which is affecting the project and has resulted in a risk
Answers
C.
The impact(s) on the project objectives should the threat or opportunity occur
C.
The impact(s) on the project objectives should the threat or opportunity occur
Answers
D.
The change in the status of a risk in response to actions taken to control it
D.
The change in the status of a risk in response to actions taken to control it
Answers
Suggested answer: C

Explanation:

The risk effect in PRINCE2 describes the potential impact on project objectives if a specific threat or opportunity were to occur. This understanding is crucial in assessing the significance of the risk and determining the appropriate management response.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which describes risk probability?

A.
Level of risks which the project can tolerate before escalating to the Project Board
A.
Level of risks which the project can tolerate before escalating to the Project Board
Answers
B.
Probable effect on the project delivering its objectives
B.
Probable effect on the project delivering its objectives
Answers
C.
Timeframe within which the risk may occur
C.
Timeframe within which the risk may occur
Answers
D.
A measure of the likelihood of the risk occurring
D.
A measure of the likelihood of the risk occurring
Answers
Suggested answer: D

Explanation:

Risk probability in PRINCE2 refers to the measure of the likelihood that a particular risk will occur. It is a fundamental aspect of risk assessment, influencing the prioritization and management of risks within the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Total 463 questions
Go to page: of 47