Question 111

Report Export Collapse

How many tasks does the product-based planning technique describe?

One
One
Two
Two
Three
Three
Four
Four
Suggested answer: D
Explanation:

The product-based planning technique described in PRINCE2 involves four tasks: writing the Project Product Description, creating the product breakdown structure, writing product descriptions, and creating the product flow diagram. These tasks collectively help in planning the project by focusing on the products that will be delivered.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Alex Rector
35 questions

Question 112

Report Export Collapse

Which is shown in a product breakdown structure?

Management stages, major products and control points
Management stages, major products and control points
In which order the products should be created
In which order the products should be created
The major products that are to be developed in a plan
The major products that are to be developed in a plan
What resources are required to develop the products
What resources are required to develop the products
Suggested answer: C
Explanation:

A product breakdown structure (PBS) in PRINCE2 is a hierarchical decomposition of the major products that are to be developed in a project. It helps in visualizing all the products (deliverables) that are required for the project, ensuring that all products are identified and nothing is overlooked. The PBS does not indicate the order of product creation, resource requirements, or control points, but strictly the products needed.

Reference: PRINCE2 7 Foundation study guide and resources.

asked 23/09/2024
Anton Khodyakov
50 questions

Question 113

Report Export Collapse

Which statement applies to Stage Plans?

Always have the same duration as the Project Plan
Always have the same duration as the Project Plan
Are produced at the same time as the Project Initiation Documentation
Are produced at the same time as the Project Initiation Documentation
Assist the Project Manager in the day-to-day running and control of the project
Assist the Project Manager in the day-to-day running and control of the project
Provide a baseline against which the Project Board monitor overall progress
Provide a baseline against which the Project Board monitor overall progress
Suggested answer: C
Explanation:

Stage Plans in PRINCE2 are essential tools for the Project Manager, assisting in the day-to-day management and control of the project. Each Stage Plan provides the detail needed for each management stage of the project, including what work will be done, when it will be delivered, and who will be involved, thus facilitating effective project governance on a stage-by-stage basis. They do not necessarily match the duration of the Project Plan or get produced simultaneously with the Project Initiation Documentation.

Reference: PRINCE2 7 Foundation handbook and other official documents.

asked 23/09/2024
Frank Nwabueze
41 questions

Question 114

Report Export Collapse

Which is a recommended quality review team role?

Project Manager
Project Manager
Assurance
Assurance
Project Support
Project Support
Administrator
Administrator
Suggested answer: D
Explanation:

In PRINCE2 quality review meetings, the recommended roles include a Chair, Presenter, Reviewer, and an Administrator. The Administrator is crucial as they organize the logistics of the review meeting, ensure that the necessary materials are provided to the participants in advance, and take on the responsibility of recording results and follow-up actions. Project Manager, Assurance, and Project Support do not specifically align with the roles within a quality review team.

Reference: PRINCE2 7 Foundation resources and study materials.

asked 23/09/2024
Simon Merlin AGHOKENG
45 questions

Question 115

Report Export Collapse

Which is a recommended quality review team role?

Project Manager
Project Manager
Assurance
Assurance
Chair
Chair
Producer
Producer
Suggested answer: C
Explanation:

Within the context of a PRINCE2 quality review meeting, the role of Chair is recommended and crucial. The Chair's responsibility is to ensure that the review meeting is conducted methodically and remains focused on its objectives. This includes leading the discussion, ensuring that all issues are aired and discussed properly, and that the meeting runs within its allocated time. This role is distinct from that of the Project Manager, Assurance, and Producer.

Reference: PRINCE2 7 Foundation study guide and official documents.

asked 23/09/2024
darren cain
34 questions

Question 116

Report Export Collapse

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

controls
controls
products
products
project management team
project management team
stages
stages
Suggested answer: B
Explanation:

The Quality theme in PRINCE2 ensures that the project's products meet the required standards and fulfill the business needs. This theme guides the management and control of quality throughout the project, emphasizing the importance of delivering products that align with the business's expectations.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Sanjay R Khiani
47 questions

Question 117

Report Export Collapse

Which is a purpose of a Project Product Description?

Records the costs and timescales for delivery of the project's final product
Records the costs and timescales for delivery of the project's final product
Shows the dependencies between the project's products to aid planning
Shows the dependencies between the project's products to aid planning
Provides a list of all the products to be delivered by the project
Provides a list of all the products to be delivered by the project
Defines what the project must deliver in order to gain acceptance
Defines what the project must deliver in order to gain acceptance
Suggested answer: D
Explanation:

The Project Product Description is a key document in the PRINCE2 methodology that outlines the purpose, composition, derivation, and acceptance criteria of the project's main deliverable. It is crucial for defining what the project needs to deliver to be considered successful and to receive formal acceptance.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Kumail Alsinan
46 questions

Question 118

Report Export Collapse

Which of the following statements about quality assurance and Project Assurance is true?

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Suggested answer: D
Explanation:

Project Assurance in PRINCE2 is focused on the project's adherence to standards and procedures within the project environment, providing a project-level view of compliance. In contrast, Quality Assurance is an organizational level function that oversees compliance across all projects and operations, ensuring that the entire organization follows the prescribed standards.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Oeurn Chan
31 questions

Question 119

Report Export Collapse

Who carries out audits that are independent of the project?

Quality assurance
Quality assurance
Project Assurance
Project Assurance
Project Support
Project Support
Project Manager
Project Manager
Suggested answer: A
Explanation:

Quality assurance is responsible for carrying out independent audits within a project. These audits are designed to ensure that the project complies with external standards and internal policies at an organizational level, distinct from the project-focused activities.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Shady Mohamed Ibrahim
35 questions

Question 120

Report Export Collapse

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

a solution should be designed for
a solution should be designed for
an issue should be created for
an issue should be created for
the agreed actions should be recorded for
the agreed actions should be recorded for
the chair will approve the solution to
the chair will approve the solution to
Suggested answer: C
Explanation:

During a quality review meeting in PRINCE2, it is critical that any agreed actions for identified defects are recorded. This ensures that there is clarity on what is to be done, by whom, and by when, to address these defects.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.