PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 6
List of questions
Question 51

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Follow-on action recommendations are used to document any uncompleted work or additional actions required after the project closure. These recommendations ensure that any outstanding issues or incomplete deliverables are addressed, even after the project has officially closed.
Reference: PRINCE2 Foundation official study guide and materials.
These responses are crafted based on the official PRINCE2 guidelines and documentation, ensuring that they are reflective of the most current practices within the PRINCE2 methodology.
Question 52

Which is an objective of the Closing a Project process?
The objective of the Closing a Project process in PRINCE2 includes reviewing the performance of the project against its baseline. This ensures that all objectives have been achieved, the project has delivered the required products, and stakeholders are satisfied with the outcomes. It provides a formal closure to the project by ensuring all project work is completed and assessed.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 53

Which is a purpose of the Controlling a Stage process?
The purpose of the Controlling a Stage process in PRINCE2 is to monitor and control a stage by managing work progress, assessing issues and risks, and ensuring that deviations from the plan are identified and managed within tolerance. It includes taking corrective actions when necessary to keep the project on track.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 54

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
The Controlling a Stage process in PRINCE2 ensures focus on the delivery of a stage's products while managing and controlling any potential deviations or issues. This process helps in avoiding uncontrolled changes and maintains the project's focus on its objectives by providing regular monitoring and control.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 55

Which process is triggered towards the end of the final stage when all the assigned work has been completed?
The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 56

Which is a purpose of the Controlling a Stage process?
The purpose of the Controlling a Stage process in PRINCE2 is to monitor and control a stage within its authorized tolerances. During this process, the Project Manager assigns work, monitors work progress, deals with issues, reports stage status to the Project Board, and takes necessary corrective actions to stay within the stage's tolerances.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 57

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage's products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 58

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
In PRINCE2, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 59

Which is a purpose of the Directing a Project process?
The purpose of the Directing a Project process is for the Project Board to delegate the day-to-day management of the project to the Project Manager, providing the overall direction and management of the project lifecycle. This process is critical for enabling the Project Manager to run the project on behalf of the Project Board within the constraints set out by them.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 60

Which is a purpose of the Directing a Project process?
The purpose of the Directing a Project process in PRINCE2 is to enable the Project Board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This ensures that the Project Board can make key decisions and remain accountable for the project's success while not being involved in the lower-level, day-to-day activities.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question