Question 41

Report Export Collapse

Which should be funded from a change budget?

The Starting up a Project process
The Starting up a Project process
A fallback plan
A fallback plan
An agreed change to the scope of a project
An agreed change to the scope of a project
A change to a plan, within allocated tolerances, due to poor estimating
A change to a plan, within allocated tolerances, due to poor estimating
Suggested answer: C
Explanation:

Similar to the answer to question 11, the change budget is specifically allocated for changes that are agreed upon that modify the scope of the project. This ensures that any scope modifications are funded without compromising the existing budget for planned deliverables.

Reference: PRINCE2 Foundation official study guide and online resources.

asked 23/09/2024
PRABHAT VAIBHAV
34 questions

Question 42

Report Export Collapse

Which is the Issue Register NOT used for?

Capture external events that are impacting a stage
Capture external events that are impacting a stage
Record information about a deviation in stage tolerance
Record information about a deviation in stage tolerance
Capture any threats or opportunities that might have an impact on a stage
Capture any threats or opportunities that might have an impact on a stage
Record any problems identified when authorizing a Work Package
Record any problems identified when authorizing a Work Package
Suggested answer: A
Explanation:

The Issue Register in PRINCE2 is used to capture and record all issues that may affect the project but it is not designed to capture external events unless they become issues directly impacting project deliverables or processes. Its primary function is to log problems identified in project execution, not general external events.

Reference: PRINCE2 Foundation official study guide and online resources.

asked 23/09/2024
EVA LITA
44 questions

Question 43

Report Export Collapse

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Checkpoint Report
Checkpoint Report
Highlight Report
Highlight Report
Issue Report
Issue Report
Product Status Account
Product Status Account
Suggested answer: C
Explanation:

When the Project Board instructs the Project Manager to implement a request for change, details of that change are contained in an Issue Report. This document provides a detailed description of the issue, its evaluation, and the decisions regarding its resolution, including any changes to be implemented.

Reference: PRINCE2 Foundation official study guide and online resources.

These answers are based on the latest materials and guidelines from the PRINCE2 Foundation documentation and should reflect the most current practices and theoretical underpinnings of the methodology.

asked 23/09/2024
samuel crook
49 questions

Question 44

Report Export Collapse

Which is the purpose of the Change theme?

Prevent change to baselined products
Prevent change to baselined products
Identify, assess and control any potential and approved changes to baselined products
Identify, assess and control any potential and approved changes to baselined products
Establish mechanisms to monitor and compare actual achievements against those planned
Establish mechanisms to monitor and compare actual achievements against those planned
Assess and control uncertainty
Assess and control uncertainty
Suggested answer: B
Explanation:

The purpose of the Change theme in PRINCE2 is to establish a clear, structured approach for identifying, assessing, and controlling changes to baselined products. This theme ensures that only approved changes are implemented, helping to manage and minimize their potential impacts on the project's objectives.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Dennis Spring
51 questions

Question 45

Report Export Collapse

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

Capture
Capture
Examine
Examine
Propose
Propose
Decide
Decide
Suggested answer: B
Explanation:

In the issue and change control procedure within PRINCE2, the 'Examine' step involves considering alternative options to address an issue that is being managed formally. This step is crucial for evaluating the possible responses to an issue before making a decision on the best course of action.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Francisco Julian Mota Fraile
45 questions

Question 46

Report Export Collapse

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Raise a request for change
Raise a request for change
Raise an off-specification
Raise an off-specification
Write an Exception Report
Write an Exception Report
Amend the Work Package
Amend the Work Package
Suggested answer: B
Explanation:

When a product cannot meet all the requirements specified in its baselined Product Description, the first action to take is to raise an off-specification. An off-specification is used in PRINCE2 to formally identify any forecasted deviation from the agreed product requirements or quality expectations.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Suraj Patil
39 questions

Question 47

Report Export Collapse

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Only 1 is true
Only 1 is true
Only 2 is true
Only 2 is true
Both 1 and 2 are true
Both 1 and 2 are true
Neither 1 or 2 are true
Neither 1 or 2 are true
Suggested answer: B
Explanation:

The statement that 'The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved' is true. This process is crucial for ensuring that the project has met its objectives and that all remaining project deliverables are acceptable to stakeholders. The first statement is incorrect as the receipt of completed Work Packages is typically handled during the 'Managing a Stage Boundary' process rather than in the 'Closing a Project' process.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Wasawatt Ch
42 questions

Question 48

Report Export Collapse

What takes place during the Closing a Project process?

The post-project benefits reviews are performed
The post-project benefits reviews are performed
Ownership of the project's products is transferred to the customer
Ownership of the project's products is transferred to the customer
An End Stage Report is prepared for the final stage
An End Stage Report is prepared for the final stage
The project closure notification is reviewed and approved
The project closure notification is reviewed and approved
Suggested answer: B
Explanation:

During the Closing a Project process in PRINCE2, the ownership of the project's products is formally transferred to the customer, ensuring that all deliverables have been accepted and are ready for operational use. This transfer marks the formal completion of the project.

Reference: PRINCE2 Foundation official study guide and materials.

asked 23/09/2024
Puth Sovann
51 questions

Question 49

Report Export Collapse

Which is an objective of the Closing a Project process?

Prepare the plan for the next stage
Prepare the plan for the next stage
Assess any benefits that have already been realized
Assess any benefits that have already been realized
Produce a Benefits Review Plan to identify what benefits are expected
Produce a Benefits Review Plan to identify what benefits are expected
Check that all benefits are realized before closing a project
Check that all benefits are realized before closing a project
Suggested answer: C
Explanation:

One of the objectives of the Closing a Project process is to produce a Benefits Review Plan. This plan outlines how the benefits of the project will be measured and reviewed after the project has been closed. It is crucial for ensuring that the benefits expected from the project are tracked and assessed in the post-project phase.

Reference: PRINCE2 Foundation official study guide and materials.

asked 23/09/2024
Patricia Vontitte
42 questions

Question 50

Report Export Collapse

Which is a purpose of the Closing a Project process?

Authorize the final stage of the project
Authorize the final stage of the project
Confirm that all benefits defined in the Business Case have been achieved
Confirm that all benefits defined in the Business Case have been achieved
Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
Delegate day-to-day management of the end of the project to the Project Manager
Delegate day-to-day management of the end of the project to the Project Manager
Suggested answer: C
Explanation:

The purpose of the Closing a Project process is to ensure that the objectives defined in the Project Initiation Documentation (PID) have been achieved. This process involves verifying that the project's deliverables meet the objectives and that the project has fulfilled its purposes as planned.

Reference: PRINCE2 Foundation official study guide and materials.