PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 5
List of questions
Related questions
Which should be funded from a change budget?
Which is the Issue Register NOT used for?
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Which is the purpose of the Change theme?
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
What takes place during the Closing a Project process?
Which is an objective of the Closing a Project process?
Which is a purpose of the Closing a Project process?
Question