ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 3

Question list
Search
Search

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

A.
Management strategies
A.
Management strategies
Answers
B.
Plan
B.
Plan
Answers
C.
Stakeholder interests
C.
Stakeholder interests
Answers
D.
Time-driven controls
D.
Time-driven controls
Answers
Suggested answer: B

Explanation:

PRINCE2 recommends three levels of planning (Project Plan, Stage Plan, Team Plan) to reflect the needs of different levels of management involved in a project. Each plan serves a specific management purpose and addresses the needs of different management levels within the project.

Reference: PRINCE2 Foundation official documentation and study materials.

Which is a true statement about time-driven controls?

A.
Time-driven controls are used for monitoring the progress of Work Packages and management stages
A.
Time-driven controls are used for monitoring the progress of Work Packages and management stages
Answers
B.
Time-driven controls take place when specific events happen
B.
Time-driven controls take place when specific events happen
Answers
C.
Time-driven controls are produced at the end of a stage
C.
Time-driven controls are produced at the end of a stage
Answers
D.
An Exception Report is a time-driven control
D.
An Exception Report is a time-driven control
Answers
Suggested answer: A

Explanation:

Time-driven controls in PRINCE2 are specifically designed to monitor the progress of Work Packages and management stages at regular intervals. These controls ensure that the project stays on schedule and that any deviations are identified and managed promptly.

Reference: PRINCE2 Foundation official study materials.

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A.
Only 1 is true
A.
Only 1 is true
Answers
B.
Only 2 is true
B.
Only 2 is true
Answers
C.
Both 1 and 2 are true
C.
Both 1 and 2 are true
Answers
D.
Neither 1 or 2 are true
D.
Neither 1 or 2 are true
Answers
Suggested answer: C

Explanation:

Both statements are true within the PRINCE2 framework. Statement 1 is accurate as the Project Manager does have day-to-day control within the limits set by the Project Board for a management stage. Statement 2 is also correct because if a Team Manager forecasts a deviation beyond Work Package tolerances, it should indeed be referred to the Project Manager.

Reference: PRINCE2 Foundation official study materials.

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.
Progress
A.
Progress
Answers
B.
Change
B.
Change
Answers
C.
Organization
C.
Organization
Answers
D.
Quality
D.
Quality
Answers
Suggested answer: A

Explanation:

The Progress theme in PRINCE2 provides all management levels within the project management team with mechanisms for monitoring and control. It involves tracking the ongoing viability of the plans and the project's objectives, and it includes mechanisms for reporting, reviewing, and ensuring that decisions on continued investment are based on accurate information.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

A.
Corporate group
A.
Corporate group
Answers
B.
Project Board
B.
Project Board
Answers
C.
Project Assurance
C.
Project Assurance
Answers
D.
Executive
D.
Executive
Answers
Suggested answer: A

Explanation:

The information in a Lessons Report should be used by the corporate group to refine, change, and improve the standards within a quality management system. This approach ensures that insights and learnings gained from individual projects are integrated into organizational knowledge and contribute to continuous improvement across all projects.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which is a FALSE statement about technical stages?

A.
Can overlap with other technical stages
A.
Can overlap with other technical stages
Answers
B.
Typified by the use a particular set of specialist skills
B.
Typified by the use a particular set of specialist skills
Answers
C.
Include the Managing a Stage Boundary process activities
C.
Include the Managing a Stage Boundary process activities
Answers
D.
Can span more than one management stage
D.
Can span more than one management stage
Answers
Suggested answer: C

Explanation:

The statement that technical stages include the Managing a Stage Boundary process activities is false. Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

How should the Team Manager report that tolerances are forecast to be exceeded?

A.
Create an Exception Report
A.
Create an Exception Report
Answers
B.
Create a Highlight Report
B.
Create a Highlight Report
Answers
C.
Raise an issue
C.
Raise an issue
Answers
D.
Grant a concession
D.
Grant a concession
Answers
Suggested answer: A

Explanation:

The correct procedure for a Team Manager to report that tolerances are forecast to be exceeded is to create an Exception Report. This report is a crucial tool in PRINCE2 for escalating issues that cannot be resolved within the agreed tolerances, ensuring that they are brought to the attention of higher management for decision-making.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which characteristic distinguishes a project from regular business operations?

A.
Produces benefits
A.
Produces benefits
Answers
B.
Introduces business change
B.
Introduces business change
Answers
C.
Manages stakeholders
C.
Manages stakeholders
Answers
D.
Incurs cost
D.
Incurs cost
Answers
Suggested answer: B

Explanation:

A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique product, service, or result, and they often drive significant changes within an organization, unlike regular operations, which are repetitive and ongoing.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A.
Change
A.
Change
Answers
B.
Cross-functional
B.
Cross-functional
Answers
C.
Unique
C.
Unique
Answers
D.
Risk
D.
Risk
Answers
Suggested answer: C

Explanation:

The characteristic of a project that reflects different perspectives and motivations for customers and suppliers is its 'Unique' nature. Projects typically bring together diverse groups, each with distinct objectives and expectations. The uniqueness of a project involves these varied stakeholder inputs and requirements, which often need to be balanced and managed.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which product records any project outcomes perceived as negative by stakeholders?

A.
Business Case
A.
Business Case
Answers
B.
Project Plan
B.
Project Plan
Answers
C.
Communication Management Strategy
C.
Communication Management Strategy
Answers
D.
Project Product Description
D.
Project Product Description
Answers
Suggested answer: C

Explanation:

In PRINCE2, the Communication Management Strategy is the document that outlines how project communications should be managed. It includes how information will be disseminated amongst stakeholders and how feedback will be collected. Negative outcomes perceived by stakeholders are typically recorded as part of the feedback mechanism defined in the Communication Management Strategy.

Reference: PRINCE2 Foundation official guide and study material.

Total 463 questions
Go to page: of 47