PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 3
List of questions
Related questions
Question 21
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
Explanation:
PRINCE2 recommends three levels of planning (Project Plan, Stage Plan, Team Plan) to reflect the needs of different levels of management involved in a project. Each plan serves a specific management purpose and addresses the needs of different management levels within the project.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 22
Which is a true statement about time-driven controls?
Explanation:
Time-driven controls in PRINCE2 are specifically designed to monitor the progress of Work Packages and management stages at regular intervals. These controls ensure that the project stays on schedule and that any deviations are identified and managed promptly.
Reference: PRINCE2 Foundation official study materials.
Question 23
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Explanation:
Both statements are true within the PRINCE2 framework. Statement 1 is accurate as the Project Manager does have day-to-day control within the limits set by the Project Board for a management stage. Statement 2 is also correct because if a Team Manager forecasts a deviation beyond Work Package tolerances, it should indeed be referred to the Project Manager.
Reference: PRINCE2 Foundation official study materials.
Question 24
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Explanation:
The Progress theme in PRINCE2 provides all management levels within the project management team with mechanisms for monitoring and control. It involves tracking the ongoing viability of the plans and the project's objectives, and it includes mechanisms for reporting, reviewing, and ensuring that decisions on continued investment are based on accurate information.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 25
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Explanation:
The information in a Lessons Report should be used by the corporate group to refine, change, and improve the standards within a quality management system. This approach ensures that insights and learnings gained from individual projects are integrated into organizational knowledge and contribute to continuous improvement across all projects.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 26
Which is a FALSE statement about technical stages?
Explanation:
The statement that technical stages include the Managing a Stage Boundary process activities is false. Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 27
How should the Team Manager report that tolerances are forecast to be exceeded?
Explanation:
The correct procedure for a Team Manager to report that tolerances are forecast to be exceeded is to create an Exception Report. This report is a crucial tool in PRINCE2 for escalating issues that cannot be resolved within the agreed tolerances, ensuring that they are brought to the attention of higher management for decision-making.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 28
Which characteristic distinguishes a project from regular business operations?
Explanation:
A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique product, service, or result, and they often drive significant changes within an organization, unlike regular operations, which are repetitive and ongoing.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 29
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Explanation:
The characteristic of a project that reflects different perspectives and motivations for customers and suppliers is its 'Unique' nature. Projects typically bring together diverse groups, each with distinct objectives and expectations. The uniqueness of a project involves these varied stakeholder inputs and requirements, which often need to be balanced and managed.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 30
Which product records any project outcomes perceived as negative by stakeholders?
Explanation:
In PRINCE2, the Communication Management Strategy is the document that outlines how project communications should be managed. It includes how information will be disseminated amongst stakeholders and how feedback will be collected. Negative outcomes perceived by stakeholders are typically recorded as part of the feedback mechanism defined in the Communication Management Strategy.
Reference: PRINCE2 Foundation official guide and study material.
Question