Question 31

Report Export Collapse

What is the definition of a project outcome?

A measurable improvement that is perceived as an advantage by one or more stakeholders
A measurable improvement that is perceived as an advantage by one or more stakeholders
The reason for the project
The reason for the project
The result of the change derived from using the project's outputs
The result of the change derived from using the project's outputs
The project's specialist products.
The project's specialist products.
Suggested answer: C
Explanation:

According to PRINCE2, a project outcome is defined as the result of the change derived from utilizing the project's outputs. Outcomes are what the project seeks to achieve which may involve a change in the way an organization operates.

Reference: PRINCE2 Foundation official guide and study material.

asked 23/09/2024
krishamrock krishqmrock
42 questions

Question 32

Report Export Collapse

Which is NOT a purpose of a Benefits Review Plan?

Define the period over which the cost-benefit analysis will be based
Define the period over which the cost-benefit analysis will be based
Describe how to measure the performance of the project's products in operational use
Describe how to measure the performance of the project's products in operational use
Define the scope, timing and ownership of the benefit reviews required
Define the scope, timing and ownership of the benefit reviews required
Describe how to measure and confirm any benefits that are to be realised after the project is closed
Describe how to measure and confirm any benefits that are to be realised after the project is closed
Suggested answer: A
Explanation:

The Benefits Review Plan in PRINCE2 does not typically involve defining the period over which the cost-benefit analysis will be based. Its main purposes are to describe how and when the benefits of the project will be measured, including the scope, timing, and responsibility for the benefit reviews post-project closure.

Reference: PRINCE2 Foundation official guide and study material.

asked 23/09/2024
Matteo Zamori
34 questions

Question 33

Report Export Collapse

Which product documents the information needed to demonstrate continued business justification?

Business Case
Business Case
Communication Management Strategy
Communication Management Strategy
Project Product Description
Project Product Description
Quality Management Strategy
Quality Management Strategy
Suggested answer: A
Explanation:

The Business Case in PRINCE2 documents the information needed to establish and maintain a project's continued business justification. It includes details on the expected benefits, costs, risks, and the rationale for the project, providing a basis to judge whether the project remains viable.

Reference: PRINCE2 Foundation official guide and study material.

asked 23/09/2024
Mpho Ntshontsi
50 questions

Question 34

Report Export Collapse

Which is NOT a purpose of a Benefits Review Plan?

Define the period over which the cost-benefit analysis will be based
Define the period over which the cost-benefit analysis will be based
Describe how to measure the performance of the project's products in operational use
Describe how to measure the performance of the project's products in operational use
Define the scope, timing and ownership of the benefit reviews required
Define the scope, timing and ownership of the benefit reviews required
Describe how to measure and confirm any benefits that are to be realised after the project is closed
Describe how to measure and confirm any benefits that are to be realised after the project is closed
Suggested answer: A
Explanation:

This answer remains the same as question 3. The Benefits Review Plan's purpose does not typically include defining the period for the cost-benefit analysis. Instead, it focuses on outlining how the benefits of the project are to be reviewed and measured after the project's closure.

Reference: PRINCE2 Foundation official guide and study material.

These answers are derived from the official PRINCE2 documentation and study materials available for the PRINCE2 Foundation certification.

asked 23/09/2024
Corey Workman
39 questions

Question 35

Report Export Collapse

What is an off-specification?

A new requirement
A new requirement
A quality tolerance
A quality tolerance
A type of issue
A type of issue
A major risk
A major risk
Suggested answer: C
Explanation:

An off-specification in PRINCE2 is considered a type of issue that arises when a project deliverable is forecasted to deviate from its agreed-upon specifications or requirements. It is an important part of the issue and change control procedure in PRINCE2, where it's recognized and managed to ensure the project stays aligned with its objectives.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website

asked 23/09/2024
Marcel Engelbrecht
48 questions

Question 36

Report Export Collapse

Which is a type of issue?

A lesson
A lesson
A request for change
A request for change
An Exception Report
An Exception Report
A risk with an estimated high impact
A risk with an estimated high impact
Suggested answer: B
Explanation:

In the PRINCE2 framework, a type of issue that can commonly occur is a request for change. This refers to a proposal for a change or modification to any aspect of the project, which may involve changes to the project's baseline aspects such as scope, product descriptions, quality criteria, or timeframes.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website

asked 23/09/2024
Vimal Varughese
46 questions

Question 37

Report Export Collapse

Which is a typical core activity within configuration management?

Quality assurance
Quality assurance
Risk management
Risk management
Verification and audit
Verification and audit
Progress reporting
Progress reporting
Suggested answer: C
Explanation:

Verification and audit is a typical core activity within configuration management according to PRINCE2. This activity involves checking that products meet their requirements and are appropriately approved, and ensuring that all items are correctly accounted for, controlled, and both physically and logically consistent throughout the project lifecycle.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website

asked 23/09/2024
Maxime ESSIS
43 questions

Question 38

Report Export Collapse

Which is a typical core activity within configuration management?

Issue management
Issue management
Quality inspection
Quality inspection
Identification
Identification
Preparation
Preparation
Suggested answer: C
Explanation:

Identification is one of the core activities within configuration management in the PRINCE2 methodology. This activity entails defining and identifying the configuration items within a project, documenting their relationships and characteristics, and ensuring that each product's unique identity is maintained throughout the project.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website

asked 23/09/2024
Nitharsan Balanavaneethan
57 questions

Question 39

Report Export Collapse

What needs to be in place to ensure effective issue and change control?

Configuration management system
Configuration management system
Manage by exception
Manage by exception
Quality planning
Quality planning
Information needs for stakeholders
Information needs for stakeholders
Suggested answer: A
Explanation:

Effective issue and change control within a PRINCE2 project relies heavily on a configuration management system. This system tracks all items of the project, including their versions and changes, allowing for controlled changes and ensuring that all items are identified, accounted for, and monitored throughout the project.

Reference: PRINCE2 Foundation official study guide and online resources.

asked 23/09/2024
Ankitkumar Pandya
36 questions

Question 40

Report Export Collapse

Which should be funded by a change budget?

Increase in agreed scope
Increase in agreed scope
Initiation stage
Initiation stage
Change Authority
Change Authority
Handover activities
Handover activities
Suggested answer: A
Explanation:

The change budget in a PRINCE2 project is designed to fund changes that involve an increase in the agreed scope of the project. Such changes typically require additional budget allocations as they extend or modify what the project initially planned to deliver.

Reference: PRINCE2 Foundation official study guide and online resources.