What is the definition of a project outcome?
A.
A measurable improvement that is perceived as an advantage by one or more stakeholders
B.
The reason for the project
C.
The result of the change derived from using the project's outputs
D.
The project's specialist products.
Which is NOT a purpose of a Benefits Review Plan?
A.
Define the period over which the cost-benefit analysis will be based
B.
Describe how to measure the performance of the project's products in operational use
C.
Define the scope, timing and ownership of the benefit reviews required
D.
Describe how to measure and confirm any benefits that are to be realised after the project is closed
Which product documents the information needed to demonstrate continued business justification?
A.
Business Case
B.
Communication Management Strategy
C.
Project Product Description
D.
Quality Management Strategy
Which is NOT a purpose of a Benefits Review Plan?
A.
Define the period over which the cost-benefit analysis will be based
B.
Describe how to measure the performance of the project's products in operational use
C.
Define the scope, timing and ownership of the benefit reviews required
D.
Describe how to measure and confirm any benefits that are to be realised after the project is closed
What is an off-specification?
A.
A new requirement
B.
A quality tolerance
C.
A type of issue
D.
A major risk
Which is a type of issue?
A.
A lesson
B.
A request for change
C.
An Exception Report
D.
A risk with an estimated high impact
Which is a typical core activity within configuration management?
A.
Quality assurance
B.
Risk management
C.
Verification and audit
D.
Progress reporting
Which is a typical core activity within configuration management?
A.
Issue management
B.
Quality inspection
C.
Identification
D.
Preparation
What needs to be in place to ensure effective issue and change control?
A.
Configuration management system
B.
Manage by exception
C.
Quality planning
D.
Information needs for stakeholders
Which should be funded by a change budget?
A.
Increase in agreed scope
B.
Initiation stage
C.
Change Authority
D.
Handover activities
Question