Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

A.
define a coding system to provide a unique identifier for the products within
A.
define a coding system to provide a unique identifier for the products within
Answers
B.
summarize the results of the quality activities performed on
B.
summarize the results of the quality activities performed on
Answers
C.
provide a framework to design, develop and maintain
C.
provide a framework to design, develop and maintain
Answers
D.
define the project benefits to be achieved by each of
D.
define the project benefits to be achieved by each of
Answers
Suggested answer: C

Explanation:

The purpose of the Plans theme in PRINCE2 is to provide a framework to design, develop, and maintain the project's plans. This theme ensures that the project plans are aligned with the project's objectives and facilitate effective management and control of the project throughout its life cycle.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

What is the first task of product-based planning?

A.
Produce the Initiation Stage Plan
A.
Produce the Initiation Stage Plan
Answers
B.
Write the Project Product Description
B.
Write the Project Product Description
Answers
C.
Identify dependencies
C.
Identify dependencies
Answers
D.
Create the product breakdown structure
D.
Create the product breakdown structure
Answers
Suggested answer: B

Explanation:

The first task of product-based planning in PRINCE2 is to write the Project Product Description. This description defines the project's main output, outcome, or benefit and includes the project's scope and major deliverables, forming the basis for more detailed planning.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which is a benefit of using PRINCE2?

A.
Is a method specifically designed for technical projects
A.
Is a method specifically designed for technical projects
Answers
B.
Provides for the efficient and economic use of management time
B.
Provides for the efficient and economic use of management time
Answers
C.
Includes many of the proven planning techniques, such as critical path analysis
C.
Includes many of the proven planning techniques, such as critical path analysis
Answers
D.
Can be used to manage both projects and programmes
D.
Can be used to manage both projects and programmes
Answers
Suggested answer: B

Explanation:

PRINCE2 is designed to make efficient and economic use of management time, ensuring that project management is effective without being overly bureaucratic or time-consuming. This approach helps to maximize the value received from management efforts and resources.

Reference: PRINCE2 Foundation official study materials.

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A.
Specify the desired result
A.
Specify the desired result
Answers
B.
Provide the resources and skills to deliver the desired result
B.
Provide the resources and skills to deliver the desired result
Answers
C.
Pay for the project
C.
Pay for the project
Answers
D.
Specify the benefits of the project
D.
Specify the benefits of the project
Answers
Suggested answer: B

Explanation:

In the PRINCE2 customer/supplier environment, the supplier's responsibility includes providing the resources and skills necessary to deliver the desired result. This involves ensuring that the necessary personnel, technology, and other resources are available to meet the project's requirements effectively.

Reference: PRINCE2 Foundation official study materials.

Which does NOT reflect the PRINCE2 principle of continued business justification?

A.
There must be a justifiable reason for starting a project
A.
There must be a justifiable reason for starting a project
Answers
B.
The business justification drives decision making
B.
The business justification drives decision making
Answers
C.
If a project is no longer forecast to deliver a financial benefit, it should be stopped.
C.
If a project is no longer forecast to deliver a financial benefit, it should be stopped.
Answers
D.
If a project can no longer be justified, it should be stopped
D.
If a project can no longer be justified, it should be stopped
Answers
Suggested answer: C

Explanation:

The principle of continued business justification in PRINCE2 means that a project must remain justified throughout its life cycle. The key factor is the project's ongoing justification, not solely its ability to deliver financial benefits. Projects may continue for reasons other than financial gain, such as strategic importance, compliance, or public safety. Therefore, stopping a project based only on financial criteria does not reflect this principle accurately.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A.
Configuration Item Record
A.
Configuration Item Record
Answers
B.
Quality Register
B.
Quality Register
Answers
C.
Highlight Report
C.
Highlight Report
Answers
D.
Checkpoint Report
D.
Checkpoint Report
Answers
Suggested answer: C

Explanation:

The Highlight Report in PRINCE2 is used by the Project Manager to review the performance of a Work Package against its cost tolerance, among other factors. This report provides the Project Board with a summary of the stage status, and is a key tool for monitoring overall project progress, including financial performance.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A.
Only corporate or programme management
A.
Only corporate or programme management
Answers
B.
Only the Project Board
B.
Only the Project Board
Answers
C.
Only the Project Manager
C.
Only the Project Manager
Answers
D.
All levels of management
D.
All levels of management
Answers
Suggested answer: D

Explanation:

The mechanisms established by the Progress theme in PRINCE2 are used by all levels of management to control any unacceptable deviations. This includes the Project Board, Project Manager, and higher management levels, ensuring that everyone involved in the project management team can effectively monitor and control the project's progress and address issues as they arise.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which is one of the three levels of plan in PRINCE2?

A.
Benefits Review Plan
A.
Benefits Review Plan
Answers
B.
Programme Plan
B.
Programme Plan
Answers
C.
Team Plan
C.
Team Plan
Answers
D.
Project Brief
D.
Project Brief
Answers
Suggested answer: C

Explanation:

PRINCE2 defines three levels of planning: Project Plan, Stage Plan, and Team Plan. The Team Plan is one of these three levels, specifically designed to manage the delivery of the work packages assigned to the team within a management stage.

Reference: PRINCE2 Foundation official documentation and study materials.

What theme estimates the cost of delivering the project?

A.
Business Case
A.
Business Case
Answers
B.
Change
B.
Change
Answers
C.
Plans
C.
Plans
Answers
D.
Progress
D.
Progress
Answers
Suggested answer: C

Explanation:

The Plans theme in PRINCE2 is responsible for estimating the cost of delivering the project. This theme involves the development of plans that outline how, when, and by whom the project's objectives are to be achieved, including the necessary resources and associated costs.

Reference: PRINCE2 Foundation official documentation and study materials.

Which is a task of product-based planning?

A.
Identify activities and dependencies
A.
Identify activities and dependencies
Answers
B.
Write the Project Product Description
B.
Write the Project Product Description
Answers
C.
Prepare the Work Packages
C.
Prepare the Work Packages
Answers
D.
Produce Product Status Accounts
D.
Produce Product Status Accounts
Answers
Suggested answer: B

Explanation:

A task of product-based planning in PRINCE2 is to write the Project Product Description. This is part of defining and documenting the project's output, outcome, and benefits, which are crucial for planning the project effectively.

Reference: PRINCE2 Foundation official documentation and study materials.