Who represents the three project interests on a project?

A.
Project manager
Answers
A.
Project manager
B.
Project support
Answers
B.
Project support
C.
External project stakeholders
Answers
C.
External project stakeholders
D.
Project board
Answers
D.
Project board
Suggested answer: D

Explanation:

The project board in PRINCE2 represents the three project interests, which are business (value for money), user (those who will use the project's outputs), and supplier (those who provide the resources and skills). The project board is responsible for overseeing the project, ensuring that it delivers value and meets the requirements set out by these three interest groups.

Reference: PRINCE2 Foundation Handbook, Project Board section.