Question 374 - PRINCE2-7-Foundation discussion

Report
Export

Which process should be Used to confirm that the project continues to deliver against the strategic objectives?

A.
Managing a stage boundary
Answers
A.
Managing a stage boundary
B.
Managing product delivery
Answers
B.
Managing product delivery
C.
Initiating a project
Answers
C.
Initiating a project
D.
Closing a project
Answers
D.
Closing a project
Suggested answer: A

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 is designed to confirm that the project remains viable and continues to align with organizational strategic objectives. This process involves reviewing the project's performance, updating the project plan, and reconfirming the business case to ensure that the project continues to deliver value as expected.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation