Which should be provided by corporate or programme management before the Starting up a Project process commences?

A.
A Project Brief
Answers
A.
A Project Brief
B.
Sufficient information to identify the prospective Executive
Answers
B.
Sufficient information to identify the prospective Executive
C.
The Project Initiation Documentation
Answers
C.
The Project Initiation Documentation
D.
Authority to initiate a project
Answers
D.
Authority to initiate a project
Suggested answer: B

Explanation:

Before the Starting up a Project process begins, corporate or programme management should provide sufficient information to identify the prospective Executive. The Executive is a key role within the project board, responsible for overall project direction and management.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.