Question 150 - PRINCE2-7-Foundation discussion
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A.
A Project Brief
B.
Sufficient information to identify the prospective Executive
C.
The Project Initiation Documentation
D.
Authority to initiate a project