Which should be provided by a project mandate?

A.
Terms of reference
Answers
A.
Terms of reference
B.
Detailed Business Case
Answers
B.
Detailed Business Case
C.
Stage tolerances
Answers
C.
Stage tolerances
D.
Initiation Stage Plan
Answers
D.
Initiation Stage Plan
Suggested answer: A

Explanation:

The project mandate should provide the terms of reference for the project. These define the purpose and objectives of the project, setting the foundation for further project definition and planning in subsequent processes.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.