Why is a Project Brief produced?

A.
To act as a trigger for the Starting up a Project process
Answers
A.
To act as a trigger for the Starting up a Project process
B.
To record the strategies and management controls to be used by a project
Answers
B.
To record the strategies and management controls to be used by a project
C.
To provide a full and firm foundation for the initiation of a project
Answers
C.
To provide a full and firm foundation for the initiation of a project
D.
To be used by the Project Board as a basis for reviewing the progress of a project
Answers
D.
To be used by the Project Board as a basis for reviewing the progress of a project
Suggested answer: C

Explanation:

A Project Brief is produced to provide a full and firm foundation for the initiation of a project. This document outlines the project's objectives, scope, constraints, expected benefits, and structure of the project management team. It serves as the basis for the next process, Initiating a Project, where more detailed planning and definition of the project take place.

Reference: PRINCE2 7 Foundation handbook and official documents.