What is the first task of product-based planning?

A.
Produce the Initiation Stage Plan
Answers
A.
Produce the Initiation Stage Plan
B.
Write the Project Product Description
Answers
B.
Write the Project Product Description
C.
Identify dependencies
Answers
C.
Identify dependencies
D.
Create the product breakdown structure
Answers
D.
Create the product breakdown structure
Suggested answer: B

Explanation:

The first task of product-based planning in PRINCE2 is to write the Project Product Description. This description defines the project's main output, outcome, or benefit and includes the project's scope and major deliverables, forming the basis for more detailed planning.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources