What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A.
Configuration Item Record
Answers
A.
Configuration Item Record
B.
Quality Register
Answers
B.
Quality Register
C.
Highlight Report
Answers
C.
Highlight Report
D.
Checkpoint Report
Answers
D.
Checkpoint Report
Suggested answer: C

Explanation:

The Highlight Report in PRINCE2 is used by the Project Manager to review the performance of a Work Package against its cost tolerance, among other factors. This report provides the Project Board with a summary of the stage status, and is a key tool for monitoring overall project progress, including financial performance.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources