Question 21 - PRINCE2-7-Foundation discussion
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
A.
Management strategies
B.
Plan
C.
Stakeholder interests
D.
Time-driven controls