Which is a FALSE statement about technical stages?

A.
Can overlap with other technical stages
Answers
A.
Can overlap with other technical stages
B.
Typified by the use a particular set of specialist skills
Answers
B.
Typified by the use a particular set of specialist skills
C.
Include the Managing a Stage Boundary process activities
Answers
C.
Include the Managing a Stage Boundary process activities
D.
Can span more than one management stage
Answers
D.
Can span more than one management stage
Suggested answer: C

Explanation:

The statement that technical stages include the Managing a Stage Boundary process activities is false. Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources