What is an off-specification?

A.
A new requirement
Answers
A.
A new requirement
B.
A quality tolerance
Answers
B.
A quality tolerance
C.
A type of issue
Answers
C.
A type of issue
D.
A major risk
Answers
D.
A major risk
Suggested answer: C

Explanation:

An off-specification in PRINCE2 is considered a type of issue that arises when a project deliverable is forecasted to deviate from its agreed-upon specifications or requirements. It is an important part of the issue and change control procedure in PRINCE2, where it's recognized and managed to ensure the project stays aligned with its objectives.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website