Question 43 - PRINCE2-7-Foundation discussion

Report
Export

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

A.
Checkpoint Report
Answers
A.
Checkpoint Report
B.
Highlight Report
Answers
B.
Highlight Report
C.
Issue Report
Answers
C.
Issue Report
D.
Product Status Account
Answers
D.
Product Status Account
Suggested answer: C

Explanation:

When the Project Board instructs the Project Manager to implement a request for change, details of that change are contained in an Issue Report. This document provides a detailed description of the issue, its evaluation, and the decisions regarding its resolution, including any changes to be implemented.

Reference: PRINCE2 Foundation official study guide and online resources.

These answers are based on the latest materials and guidelines from the PRINCE2 Foundation documentation and should reflect the most current practices and theoretical underpinnings of the methodology.