Why is the Initiating a Project process used?

A.
To decide which project approach is suitable for the project
Answers
A.
To decide which project approach is suitable for the project
B.
To fully understand how the project objectives will be achieved before committing significant resources
Answers
B.
To fully understand how the project objectives will be achieved before committing significant resources
C.
To produce the required Work Packages
Answers
C.
To produce the required Work Packages
D.
To enable corporate or programme management to give authorization to deliver a project
Answers
D.
To enable corporate or programme management to give authorization to deliver a project
Suggested answer: B

Explanation:

The Initiating a Project process is used in PRINCE2 to ensure that there is a thorough understanding of how the project's objectives will be achieved, which includes a definition of the project's scope, benefits, risks, and approach before significant resources are committed. This process helps in establishing a clear and shared understanding of the project's basis before moving forward.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources