Which is an objective of the Managing Product Delivery process?

A.
Sign-off completed Work Packages
Answers
A.
Sign-off completed Work Packages
B.
Ensure the Business Case is kept under review
Answers
B.
Ensure the Business Case is kept under review
C.
Report progress to the Project Board
Answers
C.
Report progress to the Project Board
D.
Ensure that work on products is authorized and agreed with the team
Answers
D.
Ensure that work on products is authorized and agreed with the team
Suggested answer: D

Explanation:

An objective of the Managing Product Delivery process is to ensure that work on products is authorized and agreed with the team. This process involves the Project Manager providing Work Packages to the Team Managers, who then complete the work agreed upon within the defined tolerances.