According to PRINCE2, why might there be more than one business case for a project?

A.
There may be more than one management stage in the project
Answers
A.
There may be more than one management stage in the project
B.
The project may be in a commercial environment with a number of suppliers
Answers
B.
The project may be in a commercial environment with a number of suppliers
C.
There may be more than one work package being delivered in the project
Answers
C.
There may be more than one work package being delivered in the project
D.
The project may be in a programme environment
Answers
D.
The project may be in a programme environment
Suggested answer: D

Explanation:

In a programme environment, there might be multiple business cases within a single project, each supporting different parts of the programme's overall goals. This scenario is common when a project is designed to deliver outputs that contribute to several overlapping strategies or objectives within the programme.

Reference: PRINCE2 Foundation Handbook, Business Case Theme section.