Question 357 - PRINCE2-7-Foundation discussion
Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:
Which role should be accountable for approving these proposals?
A.
Project board
B.
Project manager
C.
Project assurance
D.
Business layer
Your answer: