Question 357 - PRINCE2-7-Foundation discussion

Report
Export

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

A.
Project board
Answers
A.
Project board
B.
Project manager
Answers
B.
Project manager
C.
Project assurance
Answers
C.
Project assurance
D.
Business layer
Answers
D.
Business layer
Suggested answer: A

Explanation:

The Project Board is accountable for approving proposals based on lessons learned from previous projects. This role involves decision-making at a higher level to ensure that the project aligns with the organization's overall strategy and governance framework. The Project Board's approval is crucial for implementing changes that can impact the project's direction and management.

Reference: PRINCE2 Foundation Guide, 'Organization' theme