Which action contributes to achieving the 'ensure continued business justification' principle?
A.
Producing separate business cases for each customer and supplier involved in the project
B.
Defining the products that the project must produce in order to control change effectively
C.
Establishing limits of authority on the project based on defined tolerances
D.
Adapting PRINCEZ to the scale of investment and the delivery approach