Question 408 - PRINCE2-7-Foundation discussion

Report
Export

Which action contributes to achieving the 'ensure continued business justification' principle?

A.
Producing separate business cases for each customer and supplier involved in the project
Answers
A.
Producing separate business cases for each customer and supplier involved in the project
B.
Defining the products that the project must produce in order to control change effectively
Answers
B.
Defining the products that the project must produce in order to control change effectively
C.
Establishing limits of authority on the project based on defined tolerances
Answers
C.
Establishing limits of authority on the project based on defined tolerances
D.
Adapting PRINCEZ to the scale of investment and the delivery approach
Answers
D.
Adapting PRINCEZ to the scale of investment and the delivery approach
Suggested answer: D

Explanation:

Achieving the principle of 'ensuring continued business justification' involves confirming that the project remains desirable, viable, and achievable throughout its lifecycle. Adapting PRINCE2 to the project's scale of investment and the chosen delivery approach helps maintain its alignment with business justification, ensuring that the project's scale, complexity, importance, capability, and risk are proportionate to the project's objectives and environment.

Reference: PRINCE2 7 Foundation handbook and documents on the principles of PRINCE2.