During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.
End Stage Report
Answers
A.
End Stage Report
B.
Team Plan
Answers
B.
Team Plan
C.
Work Package
Answers
C.
Work Package
D.
Project Plan
Answers
D.
Project Plan
Suggested answer: D

Explanation:

During the Managing a Stage Boundary process, the Project Plan is updated with the latest estimated costs and time for the upcoming stage. This ensures that the Project Plan reflects current expectations and planning realities as the project progresses.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.