Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

A.
Project mandate
Answers
A.
Project mandate
B.
Initiation stage plan
Answers
B.
Initiation stage plan
C.
Project initiation documentation
Answers
C.
Project initiation documentation
D.
Project brief
Answers
D.
Project brief
Suggested answer: D

Explanation:

The Project Brief is created during the Starting up a Project process. It defines and confirms the scope of the project, providing a foundation for the Initiation Stage and ensuring that all project stakeholders have a clear understanding of the project's objectives and scope.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.