Which is a purpose of the 'initiating a project' process?

A.
To decide if it is worthwhile to initiate a project
Answers
A.
To decide if it is worthwhile to initiate a project
B.
To decide on the project approach
Answers
B.
To decide on the project approach
C.
To establish solid foundations for a project
Answers
C.
To establish solid foundations for a project
D.
To identify the number of work packages required
Answers
D.
To identify the number of work packages required
Suggested answer: C

Explanation:

The purpose of the 'Initiating a Project' process in PRINCE2 is to establish solid foundations for the project, ensuring that there is a common understanding of the reasons for the project, the expected benefits, how it will be managed, and what its products should deliver.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.