Which is a purpose of the 'directing a project' process?

A.
To exercise overall control over the project
Answers
A.
To exercise overall control over the project
B.
To take corrective action to control risks and issues
Answers
B.
To take corrective action to control risks and issues
C.
To do the minimum in order to decide whether the project is feasible
Answers
C.
To do the minimum in order to decide whether the project is feasible
D.
To update the project plan before the next stage
Answers
D.
To update the project plan before the next stage
Suggested answer: A

Explanation:

The purpose of the 'Directing a Project' process in PRINCE2 is for the project board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This process includes decision-making on project initiation and continuation, as well as providing overall guidance on policy and standards.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.