According to the 'continued business justification' principle, what must project benefits be aligned to?

A.
Regular deliveries throughout the project
Answers
A.
Regular deliveries throughout the project
B.
The business objectives
Answers
B.
The business objectives
C.
The direction of the project board
Answers
C.
The direction of the project board
D.
The technology available
Answers
D.
The technology available
Suggested answer: B

Explanation:

According to the 'continued business justification' principle in PRINCE2, project benefits must be aligned to the business objectives. This alignment ensures that the project remains viable and relevant throughout its life cycle, and that it contributes to achieving strategic goals.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.