Which is a purpose of the 'closing a project' process?

A.
To provide the project board with information to judge the success of a stage
Answers
A.
To provide the project board with information to judge the success of a stage
B.
To confirm the project has nothing more to deliver
Answers
B.
To confirm the project has nothing more to deliver
C.
To establish mechanisms to judge whether the project is still viable
Answers
C.
To establish mechanisms to judge whether the project is still viable
D.
To establish mechanisms for forecasting project objectives
Answers
D.
To establish mechanisms for forecasting project objectives
Suggested answer: B

Explanation:

The purpose of the 'closing a project' process in PRINCE2 is to verify that all project objectives have been delivered and that the project has nothing more to deliver. It ensures that all project products have been handed over and accepted, and evaluates the performance of the project against its baselines.

Reference: PRINCE2 Foundation Handbook, Closing a Project Process section.