Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
A.
1 and 2
B.
2 and 3
C.
3 and 4
D.
1 and 4
Your answer: