Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: B

Explanation:

The purposes of the quality theme in PRINCE2 are to establish how the project will ensure that products are fit for purpose and meet stakeholder expectations (purpose 2) and to ensure that the project's objectives are desirable and achievable, which pertains to ensuring that the project has a solid business justification (purpose 3).

Reference: PRINCE2 Foundation Handbook, Quality Theme section.