Which role is responsible for the quality of the specialist products delivered in the project?

A.
Executive
Answers
A.
Executive
B.
Senior user
Answers
B.
Senior user
C.
Senior supplier
Answers
C.
Senior supplier
D.
Project assurance
Answers
D.
Project assurance
Suggested answer: C

Explanation:

In PRINCE2, the Senior Supplier role is responsible for the quality of the specialist products delivered by the project. This role represents the interests of those designing, developing, facilitating, procuring, and implementing the project's products, ensuring that the products meet the required quality standards and fit for their intended purpose.

Reference: PRINCE2 7 Foundation Handbook and official training materials.