Question 209 - PRINCE2-7-Foundation discussion
Which is a minimum requirement for applying the change theme?
A.
To establish a change budget to fund changes in scope
B.
To appoint the project manager as part of the change authority
C.
To define the project's approach to baselining products
D.
To record every issue that is raised in the issue register
Your answer: