Which is a minimum requirement for applying the change theme?

A.
To establish a change budget to fund changes in scope
Answers
A.
To establish a change budget to fund changes in scope
B.
To appoint the project manager as part of the change authority
Answers
B.
To appoint the project manager as part of the change authority
C.
To define the project's approach to baselining products
Answers
C.
To define the project's approach to baselining products
D.
To record every issue that is raised in the issue register
Answers
D.
To record every issue that is raised in the issue register
Suggested answer: D

Explanation:

A minimum requirement for applying the Change Theme in PRINCE2 is to record every issue that is raised in the issue register. This ensures that all potential and actual deviations from the plan are captured and managed appropriately, maintaining control over changes and supporting effective decision-making.

Reference: PRINCE2 7 Foundation Handbook and official training materials.