What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
A.
1 and 2
B.
2 and 3
C.
3 and 4
D.
1 and 4