Which describes an off-specification?

A.
An interdependency between products that was previously unidentified
Answers
A.
An interdependency between products that was previously unidentified
B.
The addition of an improvement to a product description
Answers
B.
The addition of an improvement to a product description
C.
A prototype demonstrating a possible design solution
Answers
C.
A prototype demonstrating a possible design solution
D.
The production of more than the defined quantity of a specialist product
Answers
D.
The production of more than the defined quantity of a specialist product
E.
That the right people are involved in appropriate roles
Answers
E.
That the right people are involved in appropriate roles
Suggested answer: D

Explanation:

An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or fails to deliver within the set tolerance levels. This could involve producing more or less of a product than was specified, or any other deviation from the product's agreed-upon specifications.

Reference: PRINCE2 7 Foundation Handbook and official training materials.