Question 220 - PRINCE2-7-Foundation discussion
Which is an objective of the 'initiating a project' process?
A.
To ensure that baselines are established and controlled
B.
To ensure that the business case is kept under review
C.
To ensure that the planned products are delivered within tolerances
D.
To ensure that user acceptance of the products is confirmed
Your answer: