What problem may occur if projects are not aligned with corporate business strategy?

A.
The control of projects may be poor
Answers
A.
The control of projects may be poor
B.
The outputs may be of poor quality
Answers
B.
The outputs may be of poor quality
C.
The objectives of different projects may overlap
Answers
C.
The objectives of different projects may overlap
D.
The project management approaches used may differ
Answers
D.
The project management approaches used may differ
Suggested answer: C

Explanation:

If projects are not aligned with the corporate business strategy, a potential problem is that the objectives of different projects may overlap. This can lead to duplicated efforts, resource wastage, and conflicts between projects, all of which detract from organizational efficiency and effectiveness.

Reference: PRINCE2 Foundation Handbook, Project Alignment with Corporate Strategy section.