Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

A.
1 and 2
Answers
A.
1 and 2
B.
2 and 3
Answers
B.
2 and 3
C.
3 and 4
Answers
C.
3 and 4
D.
1 and 4
Answers
D.
1 and 4
Suggested answer: D

Explanation:

Both Quality Assurance and Project Assurance are independent of the project manager, and they both ensure that applicable standards are used in the project. Quality Assurance is typically an external function that checks the project is using the right processes, while Project Assurance is internal to the project and provided by the project board, ensuring that the project continues to align with its objectives and the organizational environment.

Reference: PRINCE2 7 Foundation Handbook and official training materials.