Question 238 - PRINCE2-7-Foundation discussion

Report
Export

How does the project board use the 'manage by stages' principle to control the project?

A.
By approving the project management team
Answers
A.
By approving the project management team
B.
By reviewing project viability at defined intervals
Answers
B.
By reviewing project viability at defined intervals
C.
By ensuring that the benefits are managed and controlled
Answers
C.
By ensuring that the benefits are managed and controlled
D.
By reviewing previous project closure documentation
Answers
D.
By reviewing previous project closure documentation
Suggested answer: B

Explanation:

The 'Manage by Stages' principle in PRINCE2 allows the project board to control the project effectively by reviewing its viability at the end of each management stage. This review process provides regular control points where the continuation of the project is assessed based on its performance and continued business justification.

Reference: PRINCE2 7 Foundation Handbook and official training materials.