Question 243 - PRINCE2-7-Foundation discussion

Report
Export

Which process monitors work that has been assigned to a team manager?

A.
Controlling a stage
Answers
A.
Controlling a stage
B.
Directing a project
Answers
B.
Directing a project
C.
Managing a stage boundary
Answers
C.
Managing a stage boundary
D.
Managing product delivery
Answers
D.
Managing product delivery
Suggested answer: D

Explanation:

The 'Managing Product Delivery' process in PRINCE2 is designed to monitor the work assigned to a team manager. This process ensures that the work is completed according to the specifications agreed upon in the Work Package and provides a mechanism for the team manager to report progress back to the project manager.

Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.