Which is an objective of the 'directing a project' process?
A.
To tailor the project's products and roles so that the project suits the circumstances
B.
To respond to the project mandate by starting up a project
C.
To provide an interface between the project and corporate management
D.
To ensure the stage products are delivered to the stated quality standards