What is the result of the change derived from using the project's product?

A.
Benefit
Answers
A.
Benefit
B.
Dis-benefit
Answers
B.
Dis-benefit
C.
Outcome
Answers
C.
Outcome
D.
Output
Answers
D.
Output
Suggested answer: C

Explanation:

The result of the change derived from using the project's product is referred to as the 'outcome'. An outcome is the effect of the change, typically a new capability that the project's outputs enable within the organization. This differs from outputs (which are tangible deliverables of the project) and benefits (which are the measurable improvements resulting from an outcome).