Question 307 - PRINCE2-7-Foundation discussion

Report
Export

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of 'business case management technique should this be considered?

A.
Develop
Answers
A.
Develop
B.
Check
Answers
B.
Check
C.
Maintain
Answers
C.
Maintain
D.
Confirm
Answers
D.
Confirm
Suggested answer: A

Explanation:

The 'Develop' step in the 'Business Case Management' technique within PRINCE2 is where the rationale for the project is initially formulated. This includes evaluating whether current operations should continue as they are or if a change through a project could potentially enhance efficiency or effectiveness. This is the stage where strategic decisions about starting a project are made based on business justifications.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation