What 15the purpose of the 'progress! practice?

A.
To review whether the use of the products is likely to lead to the expected benefits
Answers
A.
To review whether the use of the products is likely to lead to the expected benefits
B.
To define the roles and responsibilities for monitoring progress
Answers
B.
To define the roles and responsibilities for monitoring progress
C.
To measure actual achievements against the planned time and cost targets for the project
Answers
C.
To measure actual achievements against the planned time and cost targets for the project
D.
To control events that could have a positive or negative effect on project objectives
Answers
D.
To control events that could have a positive or negative effect on project objectives
Suggested answer: C

Explanation:

The purpose of the 'Progress' practice in PRINCE2 is to provide a mechanism to monitor and compare the actual project progress against the planned objectives, particularly in terms of time and cost. This monitoring helps in identifying any deviations from the plan and facilitates timely corrective actions to keep the project on track.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

asked 23/09/2024
Andrzej Pawlus
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first