The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

A.
issue register
Answers
A.
issue register
B.
issue report
Answers
B.
issue report
C.
Issue management approach
Answers
C.
Issue management approach
D.
Risk management approach
Answers
D.
Risk management approach
Suggested answer: A

Explanation:

The project manager should review the 'issue register' to know what modifications have been proposed to an approved product during the stage. The issue register records all issues that may impact the project, including requests for change, concerns, and off-specifications, providing an overview of current and potential problems affecting project products.

Reference: PRINCE2 Foundation training materials and issue management guidance.